OAN 040/2021 – HIGH VOLTAGE ELECTRICAL MAINTENANCE – SUBSTATION G, TERMINAL 3.
OAN REF:‐ 040/2021 DATE OF ISSUE:‐ 21/10/21 EFFECTIVE DATE:‐ 03/11/21 EXPIRY DATE:‐ 03/11/21
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
On Wednesday 3rd November essential high voltage electrical maintenance work will take place within Substation G serving Terminal 3. The work will require 2x temporary electrical shutdowns of up to 30 minutes duration each. Some apron infrastructure such as Fixed Electrical Ground Power (FEGP), airbridges, and high mast lighting will be temporarily unavailable during the shutdown times.
2.0 SCOPE & LOCATION OF WORKS
2.1 The scope of work will be essential high voltage electrical maintenance work and a temporary switching of the electrical supply onto a generator whilst work is in progress, and back to mains supply upon completion of work.
2.2 All work will be located within Substation G, serving Terminal 3.
3.0 PROGRAMME
3.1 The work will take place on Wednesday 3rd November, with 2x circa 30‐minute electrical shutdowns, coordinated to avoid any operational disruption, taking place as follows:
 Circa 06:00L power will be switched on to generator supply.
 Circa 17:00L power will be switched back to main supply.
4.0 OPERATIONAL IMPLICATIONS
4.1 Whilst the 2x temporary electrical shutdowns take place, as described above, the following apron infrastructure will be unavailable:
 FEGP units on Stands 50‐55.
 Airbridges on Stands 53‐55.
 Stand Number Identification Boards (SNIB) on Stands 50‐55.
 Advanced Surface Movement Guidance & Control System (ASMGCS) antenna ‘RU10’.
 Advanced Visual Docking Guidance (AVDGS) units on Stands 50‐55.
4.2 In advance of the temporary electrical shutdowns, any aircraft connected to and drawing power from the FEGP units on Stands 50‐55 should be disconnected from the FEGP and, if required, re‐connected to a power supply from a mobile GPU.
4.3 Outside of the 2x temporary electrical shutdown periods, all affected apron infrastructure will be operating as normal.
4.4 From Tuesday 2nd November, a generator will be positioned on the Terminal 3 Head of Stand road abeam Stand 54 and will remain in‐situ until completion of works on Wednesday 3rd November.
5.0 LOW VISIBILITY PROCEDURES (LVP)
5.1 The work will have no effect on the airport’s ability to operate during periods of low visibility
 

Scottie Dog

Moderator
Staff member
Subscriber
Sep 7, 2016
3,810
360
71
Warrington
Country
Scotland
OAN 041/2021 – STAND 1 CONCRETE PAVEMENT BAY REPLACEMENTS.
OAN REF:‐ 041/2021 DATE OF ISSUE:‐ 21/10/21 EFFECTIVE DATE:‐ 01/11/21 EXPIRY DATE:‐ 02/11/21
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
Stand 1 will be closed for a period of circa 18 hours to facilitate the replacement of 2 x failed concrete pavement bays.
2.0 PROGRAMME
2.1 The programme of work will commence at 12:00L on Monday 1st November, and the stand will be ready to hand back into operation by 06:00L on Tuesday 2nd November 2021.
2.2 The overall programme will consist of circa 12 hours of concrete breakout and reinstatement activities followed by a period of circa 6 hours to allow for concrete curing and work area demarcation removal.
3.0 SCOPE & LOCATION OF WORKS
3.1 The scope of work will be to carry out the replacement of 2 x failed concrete pavement bays on Stand 1. The bays will be replaced using PQX rapid setting concrete.
4.0 OPERATIONAL IMPLICATIONS
4.1 Stand 1 will be closed for a period of circa 18 hours from 12:00L on Monday 1st until 06:00L on Tuesday 2nd November 2021.
5.0 WORK AREA DEMARCATION
5.1 A lit mobile barrier will be placed at the rear of Stand 1 during the closure period.
5.2 The area immediately surrounding the pavement bay replacement works on the closed stand will be demarked by alternate red/white interlocked blocks.
5.2.2 The blocks will be lit by low intensity, red obstacle lighting.
6.0 LOW VISIBILITY PROCEDURES (LVP)
6.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility
 

[email protected]

Active Member
Feb 20, 2018
267
43
UK
Landed from Frankfurt last night and noticed work being done on taxiway Alpha (I think) opposite the viewing park…are there any new NOTAM’s available?
 

Scottie Dog

Moderator
Staff member
Subscriber
Sep 7, 2016
3,810
360
71
Warrington
Country
Scotland
Well I've found a few moments to spare and, more importantly some wi-fi!!

Full NOTAM file until 31st December

EGCC (MANCHESTER)
Q)EGTT/QMRLC/IV/NBO/A/000/999/5321N00217W005
B)2108300431 C)2111302359
E)COVID-19 INFORMATION: RWY 05R/23L CLOSED
A3066/21
Q)EGTT/QOBCE/IV/M/AE/000/007/5329N00217W001
B)2109180100 C)2112172359
E)CRANE. CONSTRUCTION SITE CRANE OPERATING AT PSN 532831N 0021711W
(SALFORD QUAYS, SALFORD, MANCHESTER). UP TO 572FT AGL/672FT AMSL.
FOR INFO CONTACT 07854 888796. ON EXPIRY OF THIS NOTAM DETAILS WILL
BE INCLUDED IN THE UK AIP ENR 5.4 2021-09-0135/AS4
A2950/21
Q)EGTT/QFAXX/IV/NBO/AE/000/999/5324N00225W005
B)2110011800 C)2112012359
E)TREND OF REPORTED GREEN LASER EVENTS ON APPROACH TO RWY 23R.
PLEASE REPORT EVENTS TO MANCHESTER ATC IF REQUIRED
A3449/21
Q)EGTT/QOBCE/IV/M/AE/000/005/5322N00217W001
B)2110020700 C)2201021700
E)LIT CRANE OPR 532157.99N 0021634.86W 1378M, 356.23 DEG MAG FM
MANCHESTER ARP MAX HGT 428 FT AMSL, 200 FT AGL
A3430/21
Q)EGTT/QFAHX/IV/NBO/A/000/999/5321N00217W005
B)2110131010 C)2111302359
E)INCREASED BIRD ACTIVITY IN THE VCY OF THE AD IN PARTICULAR
CROSSING RWY 05L/23R
A3542/21
Q)EGTT/QOBCE/IV/M/AE/000/005/5329N00215W001
B)2110160001 C)2201132359
E)CRANE. CONSTRUCTION SITE CRANE OPERATING AT PSN 532852N 0021524W
(SALFORD, GREATER MANCHESTER). UP TO 393FT AGL/481FT AMSL. FOR INFO
CONTACT 07909 688412. ON EXPIRY OF THIS NOTAM DETAILS WILL BE
INCLUDED IN THE UK AIP ENR 5.4. 2021-10-0330/AS8
A3513/21
Q)EGTT/QFAXX/IV/NBO/A/000/999/5321N00217W005
B)2110270132 C)2201252359
E)ALL SKED PASSENGER FLIGHTS WILL BE OPR FROM TERMINAL 1 AND
TERMINAL 2
A3704/21
Q)EGTT/QWELW/IV/BO/AW/000/999/5322N00236W002
B)2111171300 C)2112242359
D)1300-2359
E)SEARCHLIGHT DISPLAY WI 1NM RADIUS 532141N 0023608W (WARRINGTON,
CHESHIRE). FOR INFO 07949 876333/07917 669060. 2021-11-0012/AS2
F)SFC G)UNL
H6710/21
Q)EGTT/QWULW/IV/BO/AW/000/006/5315N00224W001
B)2111191100 C)2111191500
E)UAS OPR WI 0.5NM RADIUS OF 531446N 0022341W (VCY ALLOSTOCK,
CHESHIRE) MAX HGT 350FT AGL. FOR INFO 07966 195281.
2021-11-0499/AS1
F)SFC G)600FT AMSL
H8217/21
Q)EGTT/QWMLW/IV/BO/AW/000/009/5316N00220W001
B)2111211900 C)2111211915
E)FIREWORK DISPLAY WI 0.5NM RADIUS 531552N 0022005W (KUTSFORD,
CHESHIRE). FOR INFO 07872 600662. 2021-11-0380/AS5
F)SFC G)830FT AMSL
H8186/21
Q)EGTT/QWELW/IV/BO/AW/000/999/5314N00236W002
B)2111221530 C)2201032359
D)1530-2359
E)SEARCHLIGHT AND LASER DISPLAY. WI 1NM RADIUS. 531340N 0023609W
(SANDIWAY, CHESHIRE). FOR INFO 07841 414793. 2021-11-0523/AS1
F)SFC G)UNL
H8299/21
Q)EGTT/QWMLW/IV/BO/AW/000/008/5319N00211W001
B)2111271915 C)2111271930
E)FIREWORK DISPLAY WI 0.5NM RADIUS 531834N 0021057W
(MACCLESFIELD, CHESHIRE). FOR INFO 07899 752600. 2021-11-0543/AS5
F)SFC G)760FT AMSL
H8263/21
SNOWTAM

FROM: 18 NOV 2021 13:37

EGCC
11181337 05L 5/5/5 100/100/100 NR/NR/NR WET/WET/WET
END.
 

Scottie Dog

Moderator
Staff member
Subscriber
Sep 7, 2016
3,810
360
71
Warrington
Country
Scotland
I have today received a number of NOTAMs that have been issued since #42. Most were for single days and have now expired, however any that are still relevant are given below:

OAN 046/2021 – NIGHT-TIME PAVEMENT REPAIRS AT RUNWAY
HOLDING POINTS A1 and J1.


OAN REF:‐ 046/2021 DATE OF ISSUE:‐ 09/11/21 EFFECTIVE DATE:‐ 22/11/21 EXPIRY DATE:‐ 27/11/21

PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF

1.0 SUMMARY
1.1 A programme of up to five night‐time shifts to carry out essential pavement repairs in the vicinity of
Runway Holding Points (RHP) A1 and J1. The repairs will take place in one location at a time. During the
nightly working hours Links Alpha or Juliet will be closed, as applicable.
2.0 PROGRAMME
2.1 Work will take place on the nights of Monday 22nd to Friday 26th November 2021, inclusive.
2.2 The planned nightly working hours will be 22:30 – 06:00L.
2.3 Subject to prevailing weather conditions, it is planned to carry out the work as follows:

 Link Juliet – 22/11/21 – 23/11/21.
 Link Alpha – 24/11/21 – 25/11/21.
N.B: Within the overall programme of work, there is provision for a single contingency shift in the event
of poor weather hampering works progress.
3.0 SCOPE & LOCATION OF WORKS
3.1 Overall, the scope of work will involve the following tasks:

 Two PQX concrete pavement repairs in the immediate vicinity of RHP J1.
 A single PQX concrete pavement repair circa 15m south of RHP A1.
 

Scottie Dog

Moderator
Staff member
Subscriber
Sep 7, 2016
3,810
360
71
Warrington
Country
Scotland
OAN 049/2021 – TAXIWAY ALPHA NIGHT-TIME PAVEMENT REPAIRS.
OAN REF:‐ 049/2021 DATE OF ISSUE:‐ 25/11/21 EFFECTIVE DATE:‐ 13/12/21 EXPIRY DATE:‐ 17/12/21
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF

1.0 SUMMARY
1.1 A programme of up to four night‐time shifts to carry out essential pavement repairs on Taxiway Alpha. During the nightly working times, Taxiway Alpha will be closed from its junction with Taxiway Bravo to east of Link Alpha‐Golf. Link Alpha‐Foxtrot and Rapid Exit Taxiways(RET) Alpha‐Echo and Bravo‐Delta will also be closed. Link Bravo will be restricted to maximum aircraft size ICAO Code C (B737/A321).

2.0 PROGRAMME
2.1 Work will take place on the nights of Monday 13th to Thursday 16th December 2021, inclusive.
2.2 The planned nightly working hours will be 23:00 – 05:30L.

3.0 SCOPE & LOCATION OF WORKS
3.1 Overall, the scope of work will involve the following tasks:
 Multiple asphalt pavement repairs.
 Re‐seating of 4 x taxiway centreline AGL fittings.
 Pavement over‐banding.

4.0 OPERATIONAL IMPLICATIONS
4.1 Runway Operations
4.1.1 Runway 05L‐23R will remain operational for the duration of the night works.

Runway 23R Operations.

4.1.2 Whilst the nightly work is in progress, the following operational considerations will apply:
 Arriving aircraft of size ICAO Code D (B767) and larger will be required to backtrack Runway 23R as directed by ATC.
 Arriving aircraft of size ICAO Code C (B737/A321) and smaller will be able to vacate Runway 23R via Link Bravo, else backtrack Runway 23R as directed by ATC.

N.B: Although Link Bravo will remain available for aircraft up to and including ICAO Code C, the adjacent RET BRAVO‐DELTA WILL BE CLOSED.

Runway 05L Operations.

4.1.3 Whilst the nightly work is in progress, the following operational considerations will apply:
 Departing aircraft of size ICAO Code D (B767) and larger will be required to backtrack Runway 05L as directed by ATC.
 Departing aircraft of Size ICAO Code C (B737/A321) and smaller may depart Runway 05L from Link Bravo (TORA 2036m), else backtrack Runway 05L as directed by ATC.

All Runway Operations

4.1.4 Flight crews of arriving or departing aircraft prohibited from using or unable to use Link Bravo should be aware that the required runway backtracking route will be between Links Alpha‐Golf and Hotel (circa 2020m).
4.2 Taxiway Restrictions
4.2.1 During the nightly working times, Taxiway Alpha will be closed from its junction with Taxiway Bravo to east of Link Alpha‐Golf. See attached drawing.
4.2.2 Outside of the nightly working times, Taxiway Alpha will be available for use.

5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 In the event of forecast low visibility, the planned night‐time work will be cancelled. Taxiway Alpha and associated runway links and exits will remain open.
5.2 In the event of un‐forecast reduced visibility conditions (meeting the criteria for LVP Alert) prevailing when work has begun, the work will be curtailed at the earliest opportunity

Screenshot (1098).png
 

Scottie Dog

Moderator
Staff member
Subscriber
Sep 7, 2016
3,810
360
71
Warrington
Country
Scotland
OAN 050/2021
SIGNATURE AVIATION APRON VIRTUAL CRITICAL PART
MONITORING EQUIPMENT INSTALLATION


OAN REF:- 050/2021 DATE OF ISSUE:- 02/12/2021 EFFECTIVE DATE:- 02/12/2021 EXPIRY DATE:- 23/02/2022
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
1.1 To upgrade existing and install new virtual Critical Part (CP) monitoring equipment for the Signature Aviation Apron.
2.0 PROGRAMME
2.1 Works are to be ongoing between 2nd December 2021 and 23rd February 2022.
2.2 Daily working hours shall be 0800-1700L.
3.0 SCOPE & LOCATION OF WORKS
3.1 Works are to install various pieces of infrastructure for the creation of a virtual CP boundary.
The following items are to be installed:
• 3 LIDAR units
• 2 wide angle thermal cameras
• 4 wide angle optical cameras
• 2 PTZ Cameras
• 1 Multisensor camera
• A mounting post for LIDAR Unit 1 Existing cameras are also to be re-aligned.
3.2 The majority of works are to take place within the vicinity of the Signature Aviation apron; within the confines of the controlled landside environment.
3.3 Some aspects of work will be located airside and will require access to the Engine Test Bay.
3.4 For a visual representation of the works, please refer to Fig.1 below.
4.0 OPERATIONAL IMPLICATIONS
4.1 The Engine Test Bay shall be closed at the following dates and times: 07/12/2021 – 10/12/2021, 1000- 1500L.
5.0 LOW VISIBILITY PROCEDURES (LVP)
5.1 Overall, the work has no impact on the airport’s ability to operate during low visibility operations.
Screenshot (1146).png
 

Scottie Dog

Moderator
Staff member
Subscriber
Sep 7, 2016
3,810
360
71
Warrington
Country
Scotland
OAN 051/2021 – SCHEDULED RUNWAY 05L-23R NIGHT-TIME MAINTENANCE CLOSURES.
OAN REF:‐ 051/2021 DATE OF ISSUE:‐ 10/12/21 EFFECTIVE DATE:‐ 11/01/22 DATE:‐ 14/01/22
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
1.1 Runway 05L‐23R will be closed for three consecutive nights in early January to facilitate essential runway maintenance works within its strip. All flight operations will take place on Runway 05R‐23L whilst work is in progress.
2.0 PROGRAMME
2.1 Work will take place on the nights of Tuesday 11th to Thursday 13th January 2022, inclusive.
2.2 The planned nightly working hours will be 22:30 – 06:00L.
3.0 SCOPE & LOCATION OF WORKS
3.1 Overall, the scope of work will involve the following tasks:
 Multiple rhinophalt and over‐banding repairs along the full length of Runway 05L‐23R.
 Pavement bay joint sealing at areas of recent repairs in vicinity of Runway Holding Points (RHP) A1 and J1.
 Routine runway maintenance tasks including rubber removal, AGL repairs and refreshment of painted ground markings.
4.0 OPERATIONAL IMPLICATIONS
4.1 Runway Operations
4.1.1 During the Runway 05L‐23R closure period (22:30‐06:00L) all flight operations will take place on Runway 05R‐23L.
4.2 Taxiway Restrictions
4.2.1 In the event of poor weather hampering the progress of Taxiway Alpha repair works as described within OAN 049/2021, those works will be rolled‐over into January, and it may be necessary to close Taxiway Alpha from east of Link Alpha‐Golf to the junction with Taxiway Bravo on the nights of Tuesday 11th – Thursday 13th January, inclusive.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 In the event of forecast low visibility, the planned work will be cancelled and Runway 05L‐23R will remain open.
5.2 In the event of un‐forecast reduced visibility conditions (meeting the criteria for LVP Alert) during the Runway 05L‐23R closure period when work has begun, the aerodrome will close to flight operations whilst the runway is recovered. An ‘AD Closed’ NOTAM will be issued in such circumstances.
 

Scottie Dog

Moderator
Staff member
Subscriber
Sep 7, 2016
3,810
360
71
Warrington
Country
Scotland
OAN 052/2021 NORTH ROAD RESURFACING
OAN REF:- 052/2021 DATE OF ISSUE:- 16/12/2021 EFFECTIVE DATE:- 06/01/2022 EXPIRY DATE:- 21/01/2022
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY A programme of up to two weeks to carry out repairs and resurfacing to parts of North Road. At times the road will be reduced to a single lane with traffic management in place.
2.0 PROGRAMME
2.1 The overall programme of work runs from Monday 10th to Friday 21st January 2022.
2.1.1 On Thursday 6th January 2022, prior to the resurfacing works commencing, an inspection involving lifting of a road plate at the T junction on North Road leading on to the airfield will be carried out.
2.2 Nominal working hours will be 07:30-18:00L.
3.0 SCOPE & LOCATION OF WORKS 3.1 All work will be located on North Road between North Gate Security and the old Operations Tower.
3.2 The overall scope of works will involve the following tasks:
• Plate removal and inspection.
• Various patches of 40mm planing and asphalt resurfacing.
• Various pit lids reseating.
• Pit realigning.
• Paint marking reinstatement.
4.0 OPERATIONAL IMPLICATIONS
4.1 Access along/through North Road will be maintained and will be controlled by a traffic light system.
4.2 Access and egress for the baggage halls will be available throughout the programme. Access/egress may change each day depending on the area being resurfaced. It will be clearly signed and agreed with the baggage management team.
4.3 Resurfacing in front of the World Duty Free (WDF) delivery bay will take place after 11:00L. The Site Supervisor for the contractor carrying out the resurfacing will telephone the delivery manager for WDF prior to any works taking place to verify that all deliveries for the day are completed.
5.0 LOW VISIBILITY OPERATIONS (LVO) 5.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility
 

Scottie Dog

Moderator
Staff member
Subscriber
Sep 7, 2016
3,810
360
71
Warrington
Country
Scotland
Current NOTAMs as at 14th January

The only item of great importance is the use of single runway operations until 1st February at 2230 and non-acceptance of diversions until 10th February at 2359. These restrictions are likely to be extended beyond those dates.

EGCC (MANCHESTER)
Q)EGTT/QFAXX/IV/NBO/A/000/999/5321N00217W005
B)2110270132 C)2201252359
E)ALL SKED PASSENGER FLIGHTS WILL BE OPR FROM TERMINAL 1 AND
TERMINAL 2
A3704/21
Q)EGTT/QOBCE/IV/M/AE/000/005/5322N00217W001
B)2112230820 C)2201311700
E)LIT CRANE OPR 532157.99N 0021634.86W 1378M, 356.23 DEG MAG FM
MANCHESTER ARP MAX HGT 428 FT AMSL, 200 FT AGL
A4391/21
Q)EGTT/QFALT/IV/NBO/A/000/999/5321N00217W005
B)2201102005 C)2202102359
E)AD NOT AVBL FOR DIVERTED TRAFFIC. EMERGENCIES EXCEPTED.

A0264/22
Q)EGTT/QMRXX/IV/NBO/A/000/999/5321N00217W005
B)2201141009 C)2202012230
E)SINGLE RWY OPS 05L/23R

A0399/22
Q)EGTT/QOBCE/IV/M/AE/000/004/5322N00213W001
B)2201170800 C)2202091800
D)0800-1800
E)LIT CRANE OPR 532132.64N 0021256.31W (3991M 081 DEG MAG FM
MANCHESTER ARP) MAX HGT 377FT AMSL 115FT AGL
A0254/22
Q)EGTT/QWELW/IV/BO/AW/000/999/5329N00214W002
B)2201191800 C)2201192359
E)LASER DISPLAY WI 1NM 532840N 0021428W (MANCHESTER, GREATER
MANCHESTER). FOR INFO 07837 582640. 2022-01-0211/AS2
F)SFC G)UNL
 