- Moderator
- #81
OAN 131/2018 – PAVEMENT RECONSTRUCTION ON STANDS 2, 4, 6 & 8.
OAN REF:‐ 131/2018 DATE OF ISSUE:‐ 21/12/18 EFFECTIVE DATE:‐ 14/01/19
EXPIRY DATE:‐ 17/05/19
1.0 SUMMARY
A programme of up to four months work to reconstruct areas of pavement on Stands 2, 4, 6 and 8. All existing asphalt surfaces will be reconstructed using pavement quality concrete. Work will take place on one stand at a time, requiring a rolling sequence of single stand closures moving progressively from Stand 8 to Stand 2.
2.0 PROGRAMME
2.1 The overall programme of work will commence on Monday 14th January 2019.
2.2 The scheduled works completion date is Friday 17th May 2019.
2.3 The work will take place Monday to Friday each week, with daily working times of 08:00 ‐ 18:00L.
2.4 During the working programme on each stand, there will be a period of circa ten days when no works activity will take place. This is to allow the newly laid concrete to cure and gain weight bearing strength.
3.0 SCOPE & LOCATION OF WORKS
3.1 All work will be located with the footprint of Stands 2, 4, 6 and 8.
3.2 Demarked work areas will be erected on one stand at a time, starting on Stand 8, moving progressively to Stand 2.
3.3 The overall scope of work incorporates the removal of the existing asphalt surfaces and replacement with pavement quality concrete.
4.0 OPERATIONAL IMPLICATION
4.1 Stand Closures
4.1.1 Stands 2 – 8 will be closed as shown on the below schedule;
Stand 8 – Monday 14th January until Friday 22nd February.
Stand 6 – Monday 25th February until Friday 22nd March.
Stand 4 – Monday 25th March until Friday 19th April.
Stand 2 – Monday 22nd April until Friday 17th May.
4.2 Parking of Ground Service Equipment
4.2.1 As work progresses from Stand 8 to Stand 2, it will be necessary to temporarily displace some parked vehicles/ equipment from Bays 10, 8A, 8, 6, 2 and 2A.
4.2.2 Any displaced vehicles/ equipment may be parked on the closed stands. Available parking areas for displaced vehicles/ equipment are shown on the attached drawings (depicted by magenta hatching).
4.3 Apron Road System
4.3.1 The individual fenced work areas will each protrude into apron road at the rear of Stands 2‐8, therefore, a small portion of the road abeam the area of work in progress will be reduced to a single operational lane.
4.3.2 Temporary traffic lights will be in place to control vehicular movement
OAN REF:‐ 131/2018 DATE OF ISSUE:‐ 21/12/18 EFFECTIVE DATE:‐ 14/01/19
EXPIRY DATE:‐ 17/05/19
1.0 SUMMARY
A programme of up to four months work to reconstruct areas of pavement on Stands 2, 4, 6 and 8. All existing asphalt surfaces will be reconstructed using pavement quality concrete. Work will take place on one stand at a time, requiring a rolling sequence of single stand closures moving progressively from Stand 8 to Stand 2.
2.0 PROGRAMME
2.1 The overall programme of work will commence on Monday 14th January 2019.
2.2 The scheduled works completion date is Friday 17th May 2019.
2.3 The work will take place Monday to Friday each week, with daily working times of 08:00 ‐ 18:00L.
2.4 During the working programme on each stand, there will be a period of circa ten days when no works activity will take place. This is to allow the newly laid concrete to cure and gain weight bearing strength.
3.0 SCOPE & LOCATION OF WORKS
3.1 All work will be located with the footprint of Stands 2, 4, 6 and 8.
3.2 Demarked work areas will be erected on one stand at a time, starting on Stand 8, moving progressively to Stand 2.
3.3 The overall scope of work incorporates the removal of the existing asphalt surfaces and replacement with pavement quality concrete.
4.0 OPERATIONAL IMPLICATION
4.1 Stand Closures
4.1.1 Stands 2 – 8 will be closed as shown on the below schedule;
Stand 8 – Monday 14th January until Friday 22nd February.
Stand 6 – Monday 25th February until Friday 22nd March.
Stand 4 – Monday 25th March until Friday 19th April.
Stand 2 – Monday 22nd April until Friday 17th May.
4.2 Parking of Ground Service Equipment
4.2.1 As work progresses from Stand 8 to Stand 2, it will be necessary to temporarily displace some parked vehicles/ equipment from Bays 10, 8A, 8, 6, 2 and 2A.
4.2.2 Any displaced vehicles/ equipment may be parked on the closed stands. Available parking areas for displaced vehicles/ equipment are shown on the attached drawings (depicted by magenta hatching).
4.3 Apron Road System
4.3.1 The individual fenced work areas will each protrude into apron road at the rear of Stands 2‐8, therefore, a small portion of the road abeam the area of work in progress will be reduced to a single operational lane.
4.3.2 Temporary traffic lights will be in place to control vehicular movement