That runway and other matters
With the news this week that BRS has increased its long term aim from 10 mppa to 15 mppa there has been a lot of talk about the airport’s future, fuelled mainly by the 60th birthday celebrations of the opening of the Lulsgate facility when it was moved from the former airport site at Whitchurch.
This week the airport has issued a press release that includes this paragraph:
Over the coming months we will be updating our existing Master Plan, setting out long-term forecasts and future infrastructure requirements, to ensure we are best placed to meet this demand and these challenges. The views of customers, employees, neighbours and other stakeholders will be essential in shaping the Airport’s future so we will be consulting widely on our current thinking later this year.”
https://www.bristolairport.co.uk/ab...bristol-airport-celebrates-60-years-of-flying
It will be interesting to see the period to be covered by the new master plan. The current one covers the period until 2015 in detail and from 2015 to 2030 on an outline basis.
Although I haven’t heard it mentioned this week I wonder whether the time has come to re-visit the case for a runway extension. The airport has always said that the matter will be kept under review and now appears ready to mount a challenge to the 10 mppa planning consents limit.
Currently the runway is 381 metres shorter than Cardiff’s 2,392 metre runway, with some saying that one of the reasons that Qatar opted to go there instead of BRS were the superior operating conditions.
In its current master plan BRS has listed several options for runway extension, all at eastern end of the airfield. However, the one that might be the most appropriate, having regard to all circumstances, is option 3 which would extend the runway by 389m with the master plan saying:
This has been assessed as the maximum extension that can be accommodated within the existing airport land. The end of the runway clear and graded area would then be at the boundary with Felton Common. The ILS localiser and, potentially approach lighting as well, would need to relocated on to the Common and a 240m by 150m area of the Common would need to come into airport control. It may be necessary to regrade parts of the Common.
The A38 would have to be dropped into a tunnel about 150 metres long as it would for the minimum option which is to extend the runway by 140 metres, and for a midway option which would see a 239 metre extension and a 150 metre starter strip, which would give runway 27 an extra 389 metres of take-off availability but only 150 metres on runway 09.
Anything beyond a runway extension of 389 metres would require significant occupation of Felton Common.
Any attempt to extend the runway would be met with intense opposition and another problem is that the common has been designated a local nature reserve by the local authority. However, with the Bristol area requiring tens of thousands of new houses in the next decade or so it seems inevitable that some of them will have to be built on Green Belt land. That might be the time to try to get some of the Green Belt land around the airport re-assigned too, so that some sort of cargo facility might then be a viable consideration.
If the airport is really serious about reaching 15 mppa in the future it seems pretty certain that it will need considerably better surface connectivity, yet more terminal space, more aircraft parking stands and, ideally, a longer runway. It might get by without the first and the last but both would open up so many more options.