Today was the latest Airport Consultative Committee meeting. Unlike a large number of members, I did attend. Unfortunately, today's meeting coincided with me meeting my old work friends for a meal at the Hawthorne Farm , (handy, being iver the road!) meaning I was home late, and so, sadly, you'll have to forgive me but it will be tomorrow when I can provide a report on the meeting.
 
Airport Consultative Committee update from 20th December 2023.

Aviation Director (Nicola McMullen) update.

A very good year, particularly the first half of the year. There has recently been a marked reduction in intended capacity due mainly to a) the delay in deliveries of aircraft to Ryanair, resulting in a number of planned services no longer operating, and b) the loss of NEO aircraft available to Wizz Air due to the Pratt& Whitney engine issues which has resulted in a reduction in services and frequency.

Nevertheless, passenger figures in October were (approximately) 386,000, November 224,000 and for December 218,000 is expected. Total passenger figures annually are expected to be +15% on pre Covid levels .

Jet2 load factor performance not as high as usual over summer due to their pricing policy .She was confident that this will improve going forward so presumably prices will be 'adjusted'.

Considerable growth with Ryanair but not as fast as expected or planned due to the aforementioned delays in delivery of new MAX airframes.

Wizz Air - Wroclaw cancelled due to inadequate passenger traffic so left to Ryanair to fullfil. Katowice cessation is temporary due to aforementioned aircraft shortages and as I previously suggested, this was due to the proximity of Katowice to the already well served Krakow.

LBA Re-Gen

This is the name now given to the terminal works, apron and runway works.

Phase 1 - Extension - Contractors now on site remodeling the embankment , delivering equipment and cabins. Full mobilisation after Christmas and construction due to commence in January.
Completion due March 2025.

Phase 2 will commence early 2025 and complete mid 2026. No contractor for this phase and will go to separate tender.

Phase 3 (aircraft stands) will be constructed as needed dependent on success in securing new routes and operators. Location of stands is confirmed and up to an addition 10 stands will be constructed .

Confirmed again the following key details re the terminal works.

* 100,000 sq feet, over 3 levels.
* Eliminates clash points within terminal.
* Eliminates need to traverse length of terminal several times.
* Provides new central screening area with 6 lanes each of 28m length, compared to 4 lanes of 12m length now.
* Three new upgraded body scanners for every 2 lanes, so 9 in total.
* Multiple escalators/lifts from Central Screening to Airside on 1st floor.
* Relocation of domestic baggage reclaim to enlarged area at Eastern end if existing terminal .
* 77% increase in international baggage belt capacity within a spacious air conditioned area. Each belt will have a dedicated baggage dolly drop off area in the undercroft, accessed via a ramp and one way road system.
* 10 Immigration desks, all wired ready for E-gate installation when Border Force are ready.
* New accommodation for Border Force staff.
* Queuing space for Immigration increased by 300% and air conditioned.
* All toilets refurbished/enlarged and new large facilities throughout the extension area.
* Dedicated lift and departure gate for passengers with restricted mobility.
* 3 additional departure gates.
* 2 new lounges at Eastern end, one Executive, one General. Enhanced product and facilities.
* Second duty free area within extension to departure lounge.
* Bus shelter walkway reduced in length. The replacement of this does NOT form part of the project but the intention is to replace with a permanent two level pier with holding lounges, which will require planning consent!! 🤔
* New digital wayfinding signage throughout terminal.
* Further increase in size of check in hall A by 30% once central screening has relocated to the current baggage reclaim area.
*83% increase in customer seating.
* 76% increase in number of eateries and bars
* Direct jobs to increase by 1600 to 3600 in total by 2030.
* Indirect jobs increases to 8500 by 2030.
* Contribution to local economy 940m by 2030.

*In addition - runway improvement works underway which will take 8 years (winter seasons) at a cost if £50m.
* All airfield lighting to become LED
* New ground handling equipment charging facilities throughout airfield apron and undercroft.
*. Replacement of one of the two existing air bridges. The extension provides no additional airbridges, as only KLM at LBA wishes to use them, BUT the 3 additional gates will be designed to be easily converted to airbridges should airlines be secured that demand these facilities (eg Lufthansa, Air France).

Although not legally required, LBA are introducing a new Master plan in 2024.

CEO Update

Really good first half year with highest passenger throughput, highest turnover and highest profit . Second half of year impacted by Ryanair and Jet2 aircraft shortages .

Average queue time at central screening across summer was 6 minutes with 98% through in under 20 minutes.

Previous 'poor' CAA rating for passengers with restricted mobility now marked as Very Good, the highest rating.

Current operational challenge in central screening due to delays in installation of new X Ray machines. This installation is compulsory per Government by summer.
Having started on schedule, removing two lanes the manufacturer then amended the software, which requires Government sign off. This has delayed manufacture of the new machines and the two out of use lanes will now remain out of use until February at which point the other two lanes will be taken out of use. Still expected all lanes will be upgraded by end of February.
Extended queue times have resulted in 3 Jet2 flights being delayed by a maximum 15 minutes and 0 passengers have missed flights. The extended queue times are mainly an issue in just the two busiest days of the week in the morning.

Some changes coming to car parking with some being re-purposed. Medium stay in front of terminal to become short stay , which will be enlarged and re-marked.
No change to free drop off area.
Airport talking to Leeds City Highways to try and secure better car park directional signage in White House Lane (these are Council owned, not airport).

Parkway Station - meeting last week. Completion late 2026 but still talking about funding. Bolton Farm on Scotland Lane now purchased and in talks with the other farm to secure a portion of their land. Leeds City Council, typically, have yet to make up their mind about access road layout and routes . Completion of the full business case was due last week

LBA is recruiting a new post, Director of Corporate Affairs, reporting to the CEO, whose role will be to take the lead in all matters relating to PR, liaison with local residents, communities politicians, etc . (He/She has my deepest sympathy!!).

Clarified reasons behind withdrawal of original CLEUD applications and re-issue of 4 new ones, each written in a different way and each with additional evidence uncovered by LBA whilst investigating claims made by they who shall not be named. As expected, but perhaps unreasonably, LCC will, in January, ask again for any evidence from third parties. However, LBA are content with this and in no rush. Their view is that the timescale is not as important as getting the right answer, even if it takes longer . In the meantime their operations are not impacted.

Finally, on the subject of bussing passengers to the terminal. Noted some complain they are not bussed, others complain that they are, especially when parked on a stand reasonably close to the terminal. The issue is the walkway. It's two way traffic system means it's possible for inbound passengers to mix with outbound and thus is not permitted by Border Force. As a result they direct that certain inbound flights, in certain circumstances, must be bussed even though it causes delay. The future replacement of the walkway with a two level pier will resolve this situation.

That's all folks! I'm suffering from a numb middle finger now after typing this lot on a mobile phone!

Happy Christmas!! And a very Happy LBA New Year!
 
Last edited:
Airport Consultative Committee update from 20th December 2023.

Aviation Director (Nicola McMullen) update.

A very good year, particularly the first half of the year. There has recently been a marked reduction in intended capacity due mainly to a) the delay in deliveries of aircraft to Ryanair, resulting in a number of planned services no longer operating, and b) the loss of NEO aircraft available to Wizz Air due to the Pratt& Whitney engine issues which has resulted in a reduction in services and frequency.

Nevertheless, passenger figures in October were (approximately) 386,000, November 224,000 and for December 218,000 is expected. Total passenger figures annually are expected to be +15% on pre Covid levels .

Jet2 load factor performance not as high as usual over summer due to their pricing policy .She was confident that this will improve going forward so presumably prices will be 'adjusted'.

Considerable growth with Ryanair but not as fast as expected or planned due to the aforementioned delays in delivery of new MAX airframes.

Wizz Air - Wroclaw cancelled due to inadequate passenger traffic so left to Ryanair to fullfil. Katowice cessation is temporary due to aforementioned aircraft shortages and as I previously suggested, this was due to the proximity of Katowice to the already well served Krakow.

LBA Re-Gen

This is the name now given to the terminal works, apron and runway works.

Phase 1 - Extension - Contractors now on site remodeling the embankment , delivering equipment and cabins. Full mobilisation after Christmas and construction due to commence in January.
Completion due March 2025.

Phase 2 will commence early 2025 and complete mid 2026. No contractor for this phase and will go to separate tender.

Phase 3 (aircraft stands) will be constructed as needed dependent on success in securing new routes and operators. Location of stands is confirmed and up to an addition 10 stands will be constructed .

Confirmed again the following key details re the terminal works.

* 100,000 sq feet, over 3 levels.
* Eliminates clash points within terminal.
* Eliminates need to traverse length of terminal several times.
* Provides new central screening area with 6 lanes each of 28m length, compared to 4 lanes of 12m length now.
* Three new upgraded body scanners for every 2 lanes, so 9 in total.
* Multiple escalators/lifts from Central Screening to Airside on 1st floor.
* Relocation of domestic baggage reclaim to enlarged area at Eastern end if existing terminal .
* 77% increase in international baggage belt capacity within a spacious air conditioned area. Each belt will have a dedicated baggage dolly drop off area in the undercroft, accessed via a ramp and one way road system.
* 10 Immigration desks, all wired ready for E-gate installation when Border Force are ready.
* New accommodation for Border Force staff.
* Queuing space for Immigration increased by 300% and air conditioned.
* All toilets refurbished/enlarged and new large facilities throughout the extension area.
* Dedicated lift and departure gate for passengers with restricted mobility.
* 3 additional departure gates.
* 2 new lounges at Eastern end, one Executive, one General. Enhanced product and facilities.
* Second duty free area within extension to departure lounge.
* Bus shelter walkway reduced in length. The replacement of this does NOT form part of the project but the intention is to replace with a permanent two level pier with holding lounges, which will require planning consent!! 🤔
* New digital wayfinding signage throughout terminal.
* Further increase in size of check in hall A by 30% once central screening has relocated to the current baggage reclaim area.
*83% increase in customer seating.
* 76% increase in number of eateries and bars
* Direct jobs to increase by 1600 to 3600 in total by 2030.
* Indirect jobs increases to 8500 by 2030.
* Contribution to local economy 940m by 2030.

*In addition - runway improvement works underway which will take 8 years (winter seasons) at a cost if £50m.
* All airfield lighting to become LED
* New ground handling equipment charging facilities throughout airfield apron and undercroft.
*. Replacement of one of the two existing air bridges. The extension provides no additional airbridges, as only KLM at LBA wishes to use them, BUT the 3 additional gates will be designed to be easily converted to airbridges should airlines be secured that demand these facilities (eg Lufthansa, Air France).

Although not legally required, LBA are introducing a new Master plan in 2024.

CEO Update

Really good first half year with highest passenger throughput, highest turnover and highest profit . Second half of year impacted by Ryanair and Jet2 aircraft shortages .

Average queue time at central screening across summer was 6 minutes with 98% through in under 20 minutes.

Previous 'poor' CAA rating for passengers with restricted mobility now marked as Very Good, the highest rating.

Current operational challenge in central screening due to delays in installation of new X Ray machines. This installation is compulsory per Government by summer.
Having started on schedule, removing two lanes the manufacturer then amended the software, which requires Government sign off. This has delayed manufacture of the new machines and the two out of use lanes will now remain out of use until February at which point the other two lanes will be taken out of use. Still expected all lanes will be upgraded by end of February.
Extended queue times have resulted in 3 Jet2 flights being delayed by a maximum 15 minutes and 0 passengers have missed flights. The extended queue times are mainly an issue in just the two busiest days of the week in the morning.

Some changes coming to car parking with some being re-purposed. Medium stay in front of terminal to become short stay , which will be enlarged and re-marked.
No change to free drop off area.
Airport talking to Leeds City Highways to try and secure better car park directional signage in White House Lane (these are Council owned, not airport).

Parkway Station - meeting last week. Completion late 2026 but still talking about funding. Bolton Farm on Scotland Lane now purchased and in talks with the other farm to secure a portion of their land. Leeds City Council, typically, have yet to make up their mind about access road layout and routes . Completion of the full business case was due last week

LBA is recruiting a new post, Director of Corporate Affairs, reporting to the CEO, whose role will be to take the lead in all matters relating to PR, liaison with local residents, communities politicians, etc . (He/She has my deepest sympathy!!).

Clarified reasons behind withdrawal of original CLEUD applications and re-issue of 4 new ones, each written in a different way and each with additional evidence uncovered by LBA whilst investigating claims made by they who shall not be named. As expected, but perhaps unreasonably, LCC will, in January, ask again for any evidence from third parties. However, LBA are content with this and in no rush. Their view is that the timescale is not as important as getting the right answer, even if it takes longer . In the meantime their operations are not impacted.

Finally, on the subject of bussing passengers to the terminal. Noted some complain they are not bussed, others complain that they are, especially when parked on a stand reasonably close to the terminal. The issue is the walkway. It's two way traffic system means it's possible for inbound passengers to mix with outbound and thus is not permitted by Border Force. As a result they direct that certain inbound flights, in certain circumstances, must be bussed even though it causes delay. The future replacement of the walkway with a two level pier will resolve this situation.

That's all folks! I'm suffering from a numb middle finger now after typing this lot on a mobile phone!

Happy Christmas!! And a very Happy LBA New Year!
Wow well what a report, thankyou wh!
Things really are looking very positive indeed, also interesting to hear of a few other future plans which so far have not been mentioned inc a double pier walkway and upto now 10 extra parking stands when they become required. Made my day!
 
Thank you White Heather. As ever, a very detailed and comprehensive report. Many thanks for your hard work with this report and the others throughout the year. We are grateful for your membership of the committee to keep us up to date! Speaking as a lifelong supporter of LBA, things seem promising.
 
Just a point of interest. LBA claim that by 2030, assuming 7m passengers per year, they will add £940m to the local GVA.

Down the A1 at the closed DSA, politicians trying to justify it's re-opening are claiming that it would generate £1560m GVA to the local economy based on 2m passengers per year within 10 years, so realistically by 2035. That's £620m more than LBA that may well have 3.5 times the passenger throughput.

Me thinks someone's really gilding the lily down in South Yorkshire to get their vanity project re-opened. It sounds like complete nonsense even IF they get some freight to keep them busy.
 
Right from the start I always thought that the estimates for DSA were grossly exaggerated. I think that Peel contributed to this. The current proposals by the council seem to be a ridiculous waste of funds and I am surprised that there hasn’t been an outcry from local taxpayers! Civic pride, rather than a sober economic analysis, appear to be driving them.
 
How you managed to write that lot on a mobile keypad WH I don't know. Congrats anyway.

There are more new stands than were expected and I wonder where they all will go/ be sited. It all sounds very impressive. and I look forward to the completion. That will, as I think has been said before,be one in the eye for you know who.
 
Last edited:
How you managed to write that lot on a mobile keypad WH I don't know WH. Congrats anyway.

There are more new stands than weren't expected and I wonder where they all will go/ be sited. It all sounds very impressive. and I look forward to the completion. That will, as I think has been said before, to one in the eye for you know who.
You'll see where they go in next years Masterplan no doubt but basically alongside the taxiway (ex runway 10/28) at the mid to Eastern and, and alongside the other taxiway (ex runway 01/19 or North/South Taxiway.).
 
Airport Consultative Committee update from 20th December 2023.

Aviation Director (Nicola McMullen) update.

A very good year, particularly the first half of the year. There has recently been a marked reduction in intended capacity due mainly to a) the delay in deliveries of aircraft to Ryanair, resulting in a number of planned services no longer operating, and b) the loss of NEO aircraft available to Wizz Air due to the Pratt& Whitney engine issues which has resulted in a reduction in services and frequency.

Nevertheless, passenger figures in October were (approximately) 386,000, November 224,000 and for December 218,000 is expected. Total passenger figures annually are expected to be +15% on pre Covid levels .

Jet2 load factor performance not as high as usual over summer due to their pricing policy .She was confident that this will improve going forward so presumably prices will be 'adjusted'.

Considerable growth with Ryanair but not as fast as expected or planned due to the aforementioned delays in delivery of new MAX airframes.

Wizz Air - Wroclaw cancelled due to inadequate passenger traffic so left to Ryanair to fullfil. Katowice cessation is temporary due to aforementioned aircraft shortages and as I previously suggested, this was due to the proximity of Katowice to the already well served Krakow.

LBA Re-Gen

This is the name now given to the terminal works, apron and runway works.

Phase 1 - Extension - Contractors now on site remodeling the embankment , delivering equipment and cabins. Full mobilisation after Christmas and construction due to commence in January.
Completion due March 2025.

Phase 2 will commence early 2025 and complete mid 2026. No contractor for this phase and will go to separate tender.

Phase 3 (aircraft stands) will be constructed as needed dependent on success in securing new routes and operators. Location of stands is confirmed and up to an addition 10 stands will be constructed .

Confirmed again the following key details re the terminal works.

* 100,000 sq feet, over 3 levels.
* Eliminates clash points within terminal.
* Eliminates need to traverse length of terminal several times.
* Provides new central screening area with 6 lanes each of 28m length, compared to 4 lanes of 12m length now.
* Three new upgraded body scanners for every 2 lanes, so 9 in total.
* Multiple escalators/lifts from Central Screening to Airside on 1st floor.
* Relocation of domestic baggage reclaim to enlarged area at Eastern end if existing terminal .
* 77% increase in international baggage belt capacity within a spacious air conditioned area. Each belt will have a dedicated baggage dolly drop off area in the undercroft, accessed via a ramp and one way road system.
* 10 Immigration desks, all wired ready for E-gate installation when Border Force are ready.
* New accommodation for Border Force staff.
* Queuing space for Immigration increased by 300% and air conditioned.
* All toilets refurbished/enlarged and new large facilities throughout the extension area.
* Dedicated lift and departure gate for passengers with restricted mobility.
* 3 additional departure gates.
* 2 new lounges at Eastern end, one Executive, one General. Enhanced product and facilities.
* Second duty free area within extension to departure lounge.
* Bus shelter walkway reduced in length. The replacement of this does NOT form part of the project but the intention is to replace with a permanent two level pier with holding lounges, which will require planning consent!! 🤔
* New digital wayfinding signage throughout terminal.
* Further increase in size of check in hall A by 30% once central screening has relocated to the current baggage reclaim area.
*83% increase in customer seating.
* 76% increase in number of eateries and bars
* Direct jobs to increase by 1600 to 3600 in total by 2030.
* Indirect jobs increases to 8500 by 2030.
* Contribution to local economy 940m by 2030.

*In addition - runway improvement works underway which will take 8 years (winter seasons) at a cost if £50m.
* All airfield lighting to become LED
* New ground handling equipment charging facilities throughout airfield apron and undercroft.
*. Replacement of one of the two existing air bridges. The extension provides no additional airbridges, as only KLM at LBA wishes to use them, BUT the 3 additional gates will be designed to be easily converted to airbridges should airlines be secured that demand these facilities (eg Lufthansa, Air France).

Although not legally required, LBA are introducing a new Master plan in 2024.

CEO Update

Really good first half year with highest passenger throughput, highest turnover and highest profit . Second half of year impacted by Ryanair and Jet2 aircraft shortages .

Average queue time at central screening across summer was 6 minutes with 98% through in under 20 minutes.

Previous 'poor' CAA rating for passengers with restricted mobility now marked as Very Good, the highest rating.

Current operational challenge in central screening due to delays in installation of new X Ray machines. This installation is compulsory per Government by summer.
Having started on schedule, removing two lanes the manufacturer then amended the software, which requires Government sign off. This has delayed manufacture of the new machines and the two out of use lanes will now remain out of use until February at which point the other two lanes will be taken out of use. Still expected all lanes will be upgraded by end of February.
Extended queue times have resulted in 3 Jet2 flights being delayed by a maximum 15 minutes and 0 passengers have missed flights. The extended queue times are mainly an issue in just the two busiest days of the week in the morning.

Some changes coming to car parking with some being re-purposed. Medium stay in front of terminal to become short stay , which will be enlarged and re-marked.
No change to free drop off area.
Airport talking to Leeds City Highways to try and secure better car park directional signage in White House Lane (these are Council owned, not airport).

Parkway Station - meeting last week. Completion late 2026 but still talking about funding. Bolton Farm on Scotland Lane now purchased and in talks with the other farm to secure a portion of their land. Leeds City Council, typically, have yet to make up their mind about access road layout and routes . Completion of the full business case was due last week

LBA is recruiting a new post, Director of Corporate Affairs, reporting to the CEO, whose role will be to take the lead in all matters relating to PR, liaison with local residents, communities politicians, etc . (He/She has my deepest sympathy!!).

Clarified reasons behind withdrawal of original CLEUD applications and re-issue of 4 new ones, each written in a different way and each with additional evidence uncovered by LBA whilst investigating claims made by they who shall not be named. As expected, but perhaps unreasonably, LCC will, in January, ask again for any evidence from third parties. However, LBA are content with this and in no rush. Their view is that the timescale is not as important as getting the right answer, even if it takes longer . In the meantime their operations are not impacted.

Finally, on the subject of bussing passengers to the terminal. Noted some complain they are not bussed, others complain that they are, especially when parked on a stand reasonably close to the terminal. The issue is the walkway. It's two way traffic system means it's possible for inbound passengers to mix with outbound and thus is not permitted by Border Force. As a result they direct that certain inbound flights, in certain circumstances, must be bussed even though it causes delay. The future replacement of the walkway with a two level pier will resolve this situation.

That's all folks! I'm suffering from a numb middle finger now after typing this lot on a mobile phone!

Happy Christmas!! And a very Happy LBA New Year!7

A bit surprising that this meeting we are being told that Wroclaw had beeen axed due to disappointing bookings yet at previous meetings we have been told that Wizz were more than happy with bookings across all routes.
 
A bit surprising that this meeting we are being told that Wroclaw had beeen axed due to disappointing bookings yet at previous meetings we have been told that Wizz were more than happy with bookings across all routes.
In March I reported that Wizz were happy (generally) at LBA . This was just 4 months after transferring here bringing with them passengers who were pre booked from a time when Wizz had Wroclaw to themselves out of DSA. They had come to LBA where the route had completion in the form of Ryanair.

In June I reported that Wizz were performing strongly, with no reference to specific routes. Presumably they were doing well, but Wroclaw not up with the others. Passenger figure stats will show that

Another 6 months are gone and the route is pulled. We've seen elsewhere that due to aircraft shortages, it's not taking much for routes to be pulled if they are not performing to the same level as others. With limited aircraft, it's going to be a case of sacrificing the weakest from a profit point of view. And, much can change in terms of bookings over the last 6 months. Perhaps Ryanair offered better prices or better flight times? I wouldn't know. Perhaps, if Wizz were not having to contract due to the loss of a significant number if aircraft, they might have batted it out on Wroclaw, but we will never know that either. We still have the route to Wroclaw. In the future, Wizz might give us something else . In the future they may bring Wroclaw back. Who knows?
 
Very interesting.

It would seem people are as quick to jump to conclusions on here as they are on the SaveDSA page about Wizz flights from LBA.

The airline is still very new to LBA. If the move was a disaster for them they would've already pulled their entire operation from Leeds like they did at Cardiff.
 
Just finished work and read your report @White Heather . Thankyou again for keeping us all updated. It's great to finally see our airport moving forward with massive investment at long last. Especially with a CEO & management whom definitely seem to be on the right ball

Finally l'ld like to wish you a merry Christmas and all the best for the New Year.
 
Last edited:

Upload Media

Remove Advertisements

Subscribe to help support your favourite forum and in return we'll remove all our advertisements. Your contribution will help to pay for things like site maintenance, domain name renewals and annual server charges.



Forums4aiports
Subscribe

NEW - Profile Posts

If anyone would like to share their local airport news right here in our news area let me know so I can give you the correct permissions to do so. It only takes a couple of minutes to upload a news story with an accompanying image. The news items can then be shared on the site homepage by you. #TakePart #Forums4airports Bring the news to one place!
survived a redundancy scenario where I work for the 3rd time. Now it looks likely I will get to cover work for 2 other teams.. Pretty please for a payrise? That would be a no and so stay on the min wage.
Live in Market Bosworth and take each day as it comes......
Well it looks like I'm off to Australia and New Zealand next year! Booked with BA from Manchester via Heathrow with a stop in Singapore and returning with Air New Zealand and BA via LAX to Heathrow. Will circumnavigate the globe and be my first trans-Pacific flight. First long haul flight with BA as well and of course Air NZ.
15 years at the same company was reached the weekend before last. Not sure how they will mark the occasion apart from the compulsory payirse to minimum wage (1st rise for 2 years; i was 15% above it back then!)
Ashley.S. wrote on Sotonsean's profile.
Welcome to the forum, I was born and bred in Southampton.

Trending Hashtags

Advertisement

Back
Top Bottom
  AdBlock Detected
Sure, ad-blocking software does a great job at blocking ads, but it also blocks some useful and important features of our website. For the best possible site experience please take a moment to disable your AdBlocker.