Really informative and helpful thanks LS@MANYes, snow fleet indeed.
Unsure where they will be relocated once the new taxiway echo opens though…
Well...it's almost mid December, be interesting to see if the remainder of the TP (excluding Wetherspoons) will be complete and open before the end of the year. So we have:
* The remaining legacy T2 departure area.
* Domestic arrivals baggage hall and arrivals area (which is the T2 legacy arrivals area).
* Domestic arrivals new route from the VCC to the baggage hall.
* Dual taxiway system (Echo and Delta)…although this will be a partial completion. Available until taxiway November Bravo and then further towards Pier 1 later.
* Improvements to the drop off area at departure level - maybe relocate M&G and expand the drop off zone, also the slip road up to this level needs to be two lanes.
Thanks as always to the ever helpful @CCGE29, here is some info on the on-going works on the airfield:
There is WIP until late Jan 2026 on taxiway Lima and stands 6, 8 & 10 which, until complete, means the new section of taxiway Echo cannot open (between the STS hanger and Pier B).
Stands 309 & 310 are set to become operational by next summer (airbridge's already removed from these stands, but unsure if passengers can walk straight into the VCC or will be bussed?).
Stand 202 (where the current Jet2 building is) is a potential new stand in the future.
In T3...there is a new TP (although on a much smaller scale) with the new sports bar upstairs due to open in March 26. No real detailed info on what else we can expect in the expanded departure areas, but hopefully we won't be disappointed and improvements are also made to the arrivals areas too.
Stands 16 & 17 are currently being reconfigured to become 737M / A321 capable side by side (Code C). Stand 47 is closed for new concrete pouring and new pavement installation.
All these three stands are set to re-open by April 26.
Finally, hopefully the demolition of the cargo and freight sheds can begin early next year to make way for new remote stands (20 in total) and this would also mean the dual taxiway system can then reach it's full potential all the way to Pier 1 (taxiway Zulu).