Yes I wonder how much of that £20 million they’ve just been given is to be directly invested into the work necessary to get all the regulatory boxes ticked. So far they don’t appear to have done any recruitment for fire or ATC etc and that I would think is vital to get in position NOW. But are they waiting til funding is approved to get that ball rolling? If that’s the case then they’ll not be able to get everything in place in less than 12 months, either the necessary training and testing that would be required. It’s going to slip back regardless.
I've been saying it for ages. Spring 2026 to get fully reopened is a pipe dream. I wonder if they have even explored the lead in times to order and take delivery of essential equipment ? There's a long list of things to do:
Negotiate and secure airspace from CAA.
Reinstall approach lighting (may need new lease as understood the ground they were on was leased).
Runway repairs
Procure install and test ATC equipment.
Procure, install and test baggage scanners to meet new standards.
Procure and await delivery of airfield fire equipment.
Recruit ATC staff
Recruit and possibly train fire service staff.
Let contracts with ground handling (Swissport?)
Swissport staff recruitment
Let contracts for terminal retail units
Construction of terminal retail units
Recruitment and training of staff for retail units.
Recruitment and training of staff for baggage scanning (requires Govt Security Checks which a year ago took 16 weeks)
Recruitment and training of all general airport staff, including Management, HR, airfield management, electrical etc. many requiring security clearance.
Secure Fire Certificate
ILS calibration
General airfield checks and maintenance.
Secure airport operators licence.
Develop airport website Inc arrivals and departures board.
Let airline contracts
Route advertising and general publicity.
Car park management.
Transport to and from airport to negotiate. (bus services, taxi contracts etc).
Much of this can't really start in any meaningful way until final funding is agreed by OC. I cannot see any way that FlyDoncaster and MAI can do all of these tasks in the 9 months or so available, and I suspect recruitment may be an issue too. How many skilled professionals will give up a secure post at other airports to move ( possibly house and family too) to Doncaster to take the risk at a previously failed airport?
I wonder too how much the likes of Swissport will demand to set up another base at DSA less than 4 years after having to close one down and either lose or redistribute trained staff. They may well load their rates to reflect what they see as a risky project and to cover any future losses.