Manchester: Airport - NOTAMS/OANS

  • Thread starter Thread starter Aviador
  • Start date Start date
  • Tagged users Tagged users None
Use this prefix for new threads for Manchester Airport
OAN 022/2021 – INSTALLATION OF AIRCRAFT FUEL HYDRANT SYSTEM CATHODIC PROTECTION GROUND BED.
OAN REF:‐ 022/2021 DATE OF ISSUE:‐ 22/04/21 EFFECTIVE DATE:‐ 04/05/21 EXPIRY DATE:‐ 06/07/21
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 Overall, a programme of circa ten weeks’ work to install an aircraft fuel hydrant system cathodic protection ground bed underneath a section of pavement on Taxiway Echo. Whilst work is in progress multiple stand closures and the use of several non‐standard aircraft pushback manoeuvres will be required due to restricted taxiway capability in the vicinity of the work area. The aircraft fuel hydrant system will remain active throughout.
2.0 SCOPE & LOCATION OF WORKS
2.1 SUMMARY The overall scope of work will be as follows:
 Breakout required areas of taxiway and apron pavement.
 Installation of 1 x aircraft fuel hydrant system cathodic protection ground bed measuring approximately 30 x 2.5m.
 Attachment of new CP lug to existing pipework on Stand 71.
 Installation of new cable chases.
 Laying of new PQ concrete.
 Curing of newly laid PQ concrete.
 Pavement joint sealing.
2.2 There will be two areas of work, the first area being located on Taxiway Echo with a fenced work area (40 x 40m) being erected within the taxiway strip abeam Stand 82.
2.3 A second fenced work area will also be erected on Stand 71.
2.4 At various times during the overall works programme there will be a requirement for the contractor to carry out work outside of the demarked work areas. Such work will be managed tactically to avoid further operational disruption.
3.0 PROGRAMME
3.1 Overall, the work will commence on Tuesday 4th May and will be completed by Tuesday 6th July 2021.
3.2 The work will take place during daytime hours, nominally 08:00 ‐ 17:00L.
3.3 The phasing of works activities will take place as follows:
• Tuesday 4th May – Thursday 1st July ‐ Work will be located on Taxiway Echo.
• Friday 21st May – Tuesday 6th July ‐ Work will also be located on Stand 71.
N.B: There may be a slight variation in the above dates in the event of poor weather restricting overall works progress.
4.0 OPERATIONAL IMPLICATIONS
4.1 Taxiways
4.1.1 From Tuesday 4 th May until Thursday 1 st July, Taxiway Echo will be closed H24 abeam Stand 82 and a fenced work area will be erected. Aircraft will still be permitted to use the taxiway however it will operate as a ‘double cul‐de‐sac’ and there will not be a through‐route past Stand 82.
4.2 Aircraft Stands
4.2.1Whilst work is in progress on Taxiway Echo, the following stands will be closed H24:
 68 (C & R), 69 (L & C), 70C, 71C, 80 (all centrelines), 82 (all centrelines), 83C, 84C & 231 (all centrelines).
4.2.2 Additionally, Stand 71R will be closed H24 from Friday 21st May until Tuesday 6 th July. Stand 71L will be available for the duration of the works.
4.2.3 Whilst work is in progress on Taxiway Echo Stands 69, 70, 71, 83 and 84 will be restricted to maximum aircraft size of ICAO Code C (B737/A321).
4.3 Aircraft Pushback Manoeuvres
4.3.1 For the duration of the works programme, various non‐standard aircraft pushback manoeuvres will be required due to the lack of a through‐route for aircraft on Taxiway Echo.
4.3.2All non‐standard pushback manoeuvres are to be carried out as directed by ATC.
5.0 LOW VISIBILITY PROCEDURES (LVP)
5.1 The work will have no effect on the airport’s ability to operate during periods of low visibility.
6.0 WORK AREA DEMARCATION
6.1 The work areas will be demarked by full height heras fencing, mounted on alternate red/white base boards. The southern boundaries of the work area located on Taxiway Echo will be demarked by mobile blast screens.
6.1.1 The entirety of both work area perimeters will be lit H24 by low intensity, steady red obstacle lighting.
6.2 Portions of taxiway centreline lighting leading to/through the closed portion of Taxiway Echo will be disabled.
View attachment 23302
 
OAN 020/2021
ADVANCE VISUAL DOCKING GUIDANCE SYSTEM UPGRADE.


OAN REF:- 020/2021 DATE OF ISSUE:- 25/03/2021 EFFECTIVE DATE:- 12/04/2021
MANUAL REFERENCE(S):- N/A EXPIRY DATE:- 07/05/2021


PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF


1.0 SUMMARY

A four-week programme of work to carry out upgrades to the Advance Visual Docking Guidance System
(AVDGS) serving Terminals 1, 2 & 3.

2.0 PROGRAMME


2.1 The overall programme of work will commence on Monday 12th April and is scheduled to be completed
by Friday 7th May 2021.

2.2 The daily working hours will be 08:30-17:00L.

3.0 SCOPE & LOCATION OF WORKS

3.1 The scope of work will include:

• Installation checks,

• System calibration,

• Set up and configuration,

• Function tests,

• Verification of STOP position information.

3.2 The upgrades will be carried out on all Terminal 1, Terminal 2 and Terminal 3 Pier served stands. 4.0 OPERATIONAL IMPLICATIONS

4.1 During the working times, listed at paragraph 2.2, a series of stand closures will be required. These will be agreed each morning in consultation with Airfield Control and the Airfield Duty Manager (ADM) and will take advantage of natural gaps occurring on stands throughout the daily schedule to limit any operational impact.


P_MLEhfIB-PgV8plku_PGanY6LiCPCG1vt94UGw-JtNgKpiziGStBEyOfuqvrLbRDekH-AB3_CQ_9gJSkX2rcN4kyNYN-zPjbSJs3Uq71KI7E8gAqUS1kYnaf10FvC3SM5_1bekg
OPERATIONAL ADVICE NOTICE (OAN)


4.2 Safe access to head of stand offices will be maintained throughout the programme.
4.3 All affected stands will be fully operational outside of the daily working times.

5.0 WORK AREA DEMARCATION

5.1 The work site will be coned to provide a safe working area.

6.0 LOW VISIBILITY PROCEDURES (LVP)

6.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility
 
OAN 023/2020 – REMOVAL OF FORMER STORM ENGINEERING CABINS.


OAN REF:- 023/2020 DATE OF ISSUE:- 27/04/21 EFFECTIVE DATE:- 27/04/21
MANUAL REFERENCE(S):- N/A EXPIRY DATE:- 21/05/21


PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF


1.0 SUMMARY
1.1 An additional programme of up to four weeks’ work to complete the removal of multiple portacabins
located adjacent to the head of stand road abeam Stand 72. The work will involve disconnecting utilities
and internal strip-out prior to the cabins being loaded by crane onto transport wagons and removed
from site.

2.0 PROGRAMME

2.1 The overall programme of work commenced on Monday 15th February and is now scheduled to be
completed by Friday 21st May 2021.

2.2 Towards the end of the overall programme of works, a crane will be operating airside for four days to lift
the cabins onto transport wagons.

2.3 The crane operation will be weather dependent and will not be able to operate during periods of strong
winds.

2.4 All work will take place Monday to Friday, during daylight hours.

3.0 SCOPE & LOCATION OF WORKS

3.1 The scope of work will entail the following tasks:

• Disconnection of all utilities serving the cabins.

• Dis-assembly of external stairs.

• Crane operation to load the cabins and stair assemblies onto transport vehicles for removal from site.

3.2 All work will be located within a fenced compound in the immediate vicinity of the cabins, adjacent to the apron road system abeam the head of Stand 72.


cCbZ_PiVaB2XNVJmThN1bnO6Io7mWNAnb4oKpnSdwiQDl87jRkQA5nkoruvQJ2jmtWl0Lesg7OegX8SulcXxVa02B4YGEh1yxBJD4Z1tDDgApRBkBWkFuzhNkT1V3WZ2d3UK6cD7
OPERATIONAL ADVICE NOTICE (OAN)


4.0 OPERATIONAL IMPLICATIONS
4.1 The portion of apron road abeam the head of Stand 72 will be temporarily reduced to one operational lane whilst the crane is operating on site (four days towards the end of the overall works programme).

4.1.1 Traffic management measures will be in place to ensure safe two-way vehicle transit past the crane.

4.2 Whilst the fenced works compound is in-situ, vehicular access to the adjacent de-icing fluid tanks will be retained at all times.

4.3 To facilitate airfield access/ egress for large transport vehicles and the crane, it may be necessary to route them via the Western Maintenance Area (Fairey’s Apron).

4.4 Overall, no significant operational disruption is anticipated as a result of this work.

5.0 WORKS AREA DEMARCATION

5.1 The work area will be demarked by full height heras fencing, mounted on alternate red/white base
blocks.

5.2 Whilst the crane is operating and situated partially within the apron road, the working area will be

A
L

temporarily extended and demarked by either reflective, heavyweight cones or low-level Chapter 8
barriers.

6.0 LOW VISIBILITY PROCEDURES

6.1 The work has no impact on the airport’s ability to operate during periods of low visibility.
 
Runway 05L/23R overnight closure due WIP

Q) EGTT/QMRLC/IV/NBO/A/000/999/5321N00217W005
B) FROM: 21/06/01 21:30C) TO: 21/06/04 05:00
E) RWY 05L/23R CLSD DUE WIP, ALL FLIGHT OPERATIONS TO USE RWY
05R-23L. THE WIP WILL BE CANCELLED IN THE EVENT OF FORECASTED LVP
AND RWY 05L-23R WILL REMAIN OPEN.
SCHEDULE: 2130-0500
 
OAN 025/2021 – INSTALLATION OF AIRCRAFT FUEL HYDRANT SYSTEM CATHODIC PROTECTION GROUND BED.
OAN REF:- 025/2021 DATE OF ISSUE:- 09/06/21 EFFECTIVE DATE:- 28/06/21 EXPIRY DATE:- 25/08/21
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
Overall, a programme of circa nine weeks’ work to install the second aircraft fuel hydrant system cathodic protection ground bed. The bed will be located underneath a section of pavement on Taxiway NovemberCharlie. Whilst work is in progress multiple stand closures and the use of several non-standard aircraft pushback manoeuvres will be required due to restricted taxiway capability in the vicinity of the work area. The aircraft fuel hydrant system will remain active throughout.
2.0 SCOPE & LOCATION OF WORKS
2.1 The overall scope of work will be as follows:
• Breakout required on areas of taxiway and apron pavement.
• Installation of 1 x aircraft fuel hydrant system cathodic protection ground bed, measuring approximately 30 x 2.5m.
• Installation of 1 x new chamber on Stand 241.
• Installation of new cable chases.
• Laying of new PQ concrete.
• Curing of newly laid PQ concrete.
• Pavement joint sealing.
2.2 There will be two areas of work, the first area being located on Taxiway November-Charlie with a fenced work area (40 x 40m) being erected within the taxiway strip abeam Stand 237.
2.2.1 A second fenced work area will also be erected on Stand 241.
2.3 At various times during the overall works programme there will be a requirement for the contractor to carry out work outside of the demarked work areas. Such work will be managed tactically to avoid further operational disruption.
3.0 PROGRAMME
3.1 Overall, the work will commence on Monday 28th June and will be completed by Wednesday 25th August 2021.
3.2 The work will take place during daytime hours, nominally 08:00 - 17:00L.
4.0 OPERATIONAL IMPLICATIONS
4.1 Taxiways
4.1.1 From Monday 28th June until Wednesday 25th August 2021, Taxiway November-Charlie will be closed H24 abeam Stand 237, and a fenced work area will be erected. Aircraft will still be permitted to use the taxiway however it will operate as a ‘double cul-de-sac’ and there will not be a through-route past Stand 237.
4.2 Aircraft Stands
4.2.1 Whilst work is in progress on Taxiway November-Charlie, the following stands (all centrelines) will be closed H24:
• 80, 210, 231,237 and 241.
4.3 Aircraft Pushback Manoeuvres
4.3.1 Dependent on the area of work in progress, various non-standard aircraft pushback manoeuvres will be required due to the lack of a through-route for aircraft on Taxiway November-Charlie.
4.3.2 All non-standard pushback manoeuvres are to be carried out, as directed by ATC
 
OAN 026-2021 SOUTHERN FRONT GATES & BAGGAGE CAROUSELS RE-NUMBERING.
OAN REF:- 026/2021 DATE OF ISSUE:- 10/06/2021 EFFECTIVE DATE:- 14/06/2021 EXPIRY DATE:- Permanent
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
To make the journey for guests more intuitive when doubling back from the Terminal 1 (T1) International Departure Lounge (IDL), changes to gate numbering along the Southern Front (Gates 01, 16, 17, 18) has been identified as a wayfinding enhancement. In addition, the Terminal 3 (T3) carousels are being reassigned as T1 assets. As a result, it is necessary to change the numbering of the T3 carousels, so that they do not conflict with existing T1 carousel numbers.
2.0 PROGRAMME & SCOPE OF WORKS
2.1 Overall, the work to carry out the changes will commence on Monday 14th June and will be completed by the morning of Wednesday 16th June 2021. 2.2 The phasing of works activities will take place as follows:
• The Terminal 3 carousel re-numbering will be carried out overnight on Monday 14th June 2021.
• The Southern Front gate re-numbering will be carried out overnight on Tuesday 15th June 2021.
2.3 Chroma will be updated to reflect the reassigned Terminal 3 gates and baggage carousel numbers.
3.0 OPERATIONAL IMPLICATIONS
3.1 Terminal Changes

View attachment 23692View attachment 23691

3.2 Airfield Changes 3.2.1 There will be no changes to stand numbers on the airfield; the changes relate to Passenger Boarding Gate numbers only.
 
OAN 026-2021 SOUTHERN FRONT GATES & BAGGAGE CAROUSELS RE-NUMBERING.
OAN REF:- 026/2021 DATE OF ISSUE:- 10/06/2021 EFFECTIVE DATE:- 14/06/2021 EXPIRY DATE:- Permanent
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
To make the journey for guests more intuitive when doubling back from the Terminal 1 (T1) International Departure Lounge (IDL), changes to gate numbering along the Southern Front (Gates 01, 16, 17, 18) has been identified as a wayfinding enhancement. In addition, the Terminal 3 (T3) carousels are being reassigned as T1 assets. As a result, it is necessary to change the numbering of the T3 carousels, so that they do not conflict with existing T1 carousel numbers.
2.0 PROGRAMME & SCOPE OF WORKS
2.1 Overall, the work to carry out the changes will commence on Monday 14th June and will be completed by the morning of Wednesday 16th June 2021. 2.2 The phasing of works activities will take place as follows:
• The Terminal 3 carousel re-numbering will be carried out overnight on Monday 14th June 2021.
• The Southern Front gate re-numbering will be carried out overnight on Tuesday 15th June 2021.
2.3 Chroma will be updated to reflect the reassigned Terminal 3 gates and baggage carousel numbers.
3.0 OPERATIONAL IMPLICATIONS
3.1 Terminal Changes

View attachment 23692View attachment 23691

3.2 Airfield Changes 3.2.1 There will be no changes to stand numbers on the airfield; the changes relate to Passenger Boarding Gate numbers only.
So an aircraft taxis to stand 1 but it’s gate 35 within the terminal…that doesn’t make logical sense to me, maybe this is quite normal though…??

How many carousels are there in T1 now? The newly designated T3 carousels start at 11…I’m just confused but again might be just me 😉
 
Honestly it is so long since I flew that I'm uncertain as to the effect. However, from speaking to a friend they say that it makes sense, if you assume that T3 may not reopen for some time. On that basis I believe that the airport is trying to make signage easier for passengers as, at present gates 16, 17 and 18 are out of sequence from the main gates.

Hopefully somebody else can enlighten you further.
 
Last edited:
OAN 027/2021 – SCHEDULED RUNWAY 05L-23R
NIGHT-TIME MAINTENANCE CLOSURES.


OAN REF:‐ 027/2021 DATE OF ISSUE:‐ 23/06/21 EFFECTIVE DATE:‐ 06/07/21
MANUAL REFERENCE(S):‐ N/A EXPIRY DATE:‐ 09/07/21

PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF

1.0 SUMMARY
1.1 Runway 05L‐23R will be closed for three consecutive nights in early July to facilitate essential runway
maintenance works within its strip and on associated northside taxiways. All flight operations will take
place on Runway 05R‐23L whilst work is in progress.
2.0 PROGRAMME
2.1 Work will take place on the nights of Tuesday 6th to Thursday 8th July 2021, inclusive.
2.2 The planned nightly working hours will be 22:30 – 06:00L.
3.0 SCOPE & LOCATION OF WORKS
3.1 Overall, the scope of work will involve the following tasks:

 Multiple asphalt pavement repairs on Taxiway Alpha, in the vicinity of Intermediate Holding
Point (IHP) A3.
 PQX pavement bay replacements in the vicinity of Runway Holding Points (RHP) A1 and J1.
 Multiple areas of over‐banding along Taxiway Alpha between Link Alpha‐Golf and its junction
with Taxiway Bravo and along the length of Runway 05L‐23R.
 7 x asphalt patch repairs on Runway 05L‐23R between Links Hotel and Juliet.
 Maxi‐crete repairs in the vicinity of RHP A1.

4.0 OPERATIONAL IMPLICATIONS
4.1 Runway Operations
4.1.1 During the Runway 05L‐23R closure period (22:30‐06:00L) all flight operations will take place on Runway
05R‐23L.

OPERATIONAL
ADVICE
NOTICE

OPERATIONAL ADVICE NOTICE (OAN)

OAN 027/2021 PAGE 2 OF 15
4.2 Taxiway Restrictions
4.2.1 Taxiway Alpha, between IHP A2 and its junction with Taxiway Bravo will be closed on the nights of
Tuesday 6th to Thursday 8th June, inclusive.
4.2.2 Likewise, Taxiway Bravo will be closed on the aforementioned nights from IHP B2 to its junction with
Taxiway Alpha.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 In the event of forecast low visibility, the planned work will be cancelled and Runway 05L‐23R will remain
open.
5.2 In the event of un‐forecast reduced visibility conditions (meeting the criteria for LVP Alert) during the
Runway 05L‐23R closure period when work has begun, the aerodrome will close to flight operations
whilst the runway is recovered. An ‘AD Closed’ NOTAM will be issued in such circumstances.
 
OAN 028/2021 – BAGGAGE TOWING RESTRICTION - TRIAL.

OAN REF:- 028/2021 DATE OF ISSUE:- 13/07/2021 EFFECTIVE DATE:- 15/07/2021
MANUAL REFERENCE(S):- N/A EXPIRY DATE:- 14/08/2021

PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF

1.0 SUMMARY
1.1 Concerns over the length of towed baggage trains has been raised during routine observation and
externally by Ground Handling Agents. This specifically relates to Terminal 2 facilities.
Research into industry practice shows train length restrictions between <10m (LHR) and circa 15m (STN).
At MAN, we often see baggage trains in excess of 21m in busy operational environments with other
vehicles/pedestrian interactions.

2.0 PROGRAMME
2.1 An initial trial is to take place over a 4 week period commencing 15/07/2021. This will introduce a
restriction to the maximum length of towed baggage trains within the Terminal 2 Baggage facility.

3.0 SCOPE & LOCATION OF WORKS
3.1 The maximum towing limit within Terminal 2 Baggage Halls will be no more than 2x LD8 Trailers or 3x
other baggage trailer sizes.
3.2 Relevant to Terminal 2 Baggage Hall Operations only
3.3 The stated trial duration and scope may be altered within the validity period depending upon feedback
and outputs.
3.4 The extent of this trial does not include Terminal 1 or Terminal 3 Baggage operations although these
facilities will be reviewed.
3.5 The overall objective of the trial will be to determine the most appropriate mix of equipment for
operating within the MAN Baggage Hall environment.
3.6 Trial observations, feedback and adjustments will be managed by Airfield Safety & Compliance. Any
feedback should be directed to [email protected]

4.0 OPERATIONAL IMPLICATIONS
4.1 No more than a maximum towed limit of 2x LD8 trailers or 3x other types to be permitted within the
Terminal 2 Baggage Halls areas.

4.2 Where loads are required to be un-coupled or hold, a staging area has been made available as an interim
measure between the East and West bag hall arrivals entrance. This area will be managed by Airside
Operations.

Inbound baggage carousel 1-4 should be accessed via old East entrance
Inbound baggage carousel 5-8 should be accessed via new West entrance

5.0 WORKS AREA DEMARCATION
5.1 This Trial is limited to Terminal 2 Baggage Hall facilities only. No additional works demarcation required.

6.0 LOW VISIBILITY PROCEDURES
6.1 The work has no impact on the airport’s ability to operate during periods of low visibility.
 
OAN 029/2021 RUNWAY 05R-23L MAINTENANCE REPAIRS AND SURVEY.

OAN REF:- 029/2021 DATE OF ISSUE:- 21/07/21 EFFECTIVE DATE:- 26/07/21
MANUAL REFERENCE(S):- N/A EXPIRY DATE:- 13/08/21

PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF

1.0 SUMMARY
1.1 A three-week programme of work to carry out essential runway maintenance repairs and a walking audit
will take place on Runway 05R/23L (R2), taking advantage of the already published closure.
2.0 PROGRAMME
2.1 Work will commence on Monday 26th July and be completed by Friday 13thth August 2021 inclusive.
These dates included contingency shifts in case of adverse weather.
2.2 The planned daily working hours will be 08:00-18:00L.
3.0 SCOPE & LOCATION OF WORKS
3.1 Overall, the scope of work will involve the following tasks:

• Asphalt pavement repairs.
• Maxi-crete repairs.
• Multiple areas of over-banding.
• A walking audit of the runway.
4.0 OPERATIONAL IMPLICATIONS
4.1 Runway Operations
4.1.1 Runway 05L/23R (R1) is the primary runway in use at present and will remain so for the duration of the
works.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 In the event of forecast low visibility, the planned work will be cancelled.
 
Here are the NOTAMs as at this morning and valid until 15th September

EGCC (MANCHESTER)
Q)EGTT/QOBCE/IV/M/AE/000/008/5328N00215W001
B)2106300100 C)2109282359
E)CRANE. CONSTRUCTION SITE CRANE OPERATING AT PSN 532828N 0021501W
(MANCHESTER CITY CENTRE, GREATER MANCHESTER). UP TO 642FT AGL/754FT
AMSL. FOR INFO CONTACT 07854 888796. ON EXPIRY OF THIS NOTAM DETAILS
WILL BE INCLUDED IN THE UK AIP ENR 5.4 2021-06-0151/AS4
A1740/21
Q)EGTT/QFAHX/IV/NBO/A/000/999/5321N00217W005
B)2107231629 C)2109302359
E)INCREASED BIRD ACTIVITY IN THE VICINITY OF THE AERODROME IN
PARTICULAR CROSSING RWY 05L-23R
A2642/21
Q)EGTT/QFFCG/IV/NBO/A/000/999/5321N00217W005
B)2107311939 C)2108312359
E)COVID-19 INFORMATION: RFFS FIRE CAT 7 WITH ABILITY TO ACCEPT CAT
8 OR 9 UNDER REMISSION
A2744/21
Q)EGTT/QFAXX/IV/NBO/A/000/999/5321N00217W005
B)2108021515 C)2108312359
E)COVID 19 INFORMATION : ALL SCHEDULED PASSENGER FLIGHTS WILL BE
OPERATING FROM TERMINAL 1. LIVE FLIGHT TRIALS WILL BE OPERATING FROM
TERMINAL 2
A2764/21
Q)EGTT/QOBCE/IV/M/AE/000/004/5322N00217W001
B)2108040600 C)2109231700
D)0600-1700
E)LIT CRANE OPERATING 532136.3387N 0021704.8546W, (958M 317.60 DEG
MAG FM MANCHESTER ARP) MAX HGT 396FT AMSL, 174FT AGL
A2777/21
Q)EGTT/QFUAU/IV/NBO/A/000/999/5321N00217W005
B)2108111130 C)2108312359
E)HYDRANT AIRCRAFT FUEL NOT AVBL ON STANDS 61-65
A2887/21
Q)EGTT/QMRLC/IV/NBO/A/000/999/5321N00217W005
B)2108111410 C)2108312359
E)RWY 05R/23L NOT AVAILABLE FOR USE
A2893/21
Q)EGTT/QFATT/IV/BO/A/000/999/5321N00217W005
B)2108120000 C)2108252359
E)TRIGGER NOTAM - PERM AIRAC AIP AMDT 08/21 WEF 12 AUG 21.
FLIGHT PROCEDURES - VISUAL REFERENCE POINTS (VRP) UPDATED. AD 2.22
REMOVAL OF HOLMES CHAPEL VRP, NEW M6 SANDBACH SERVICES VRP.
AD 2 EGCC 4-1
A2310/21
Q)EGTT/QMXXX/IV/M/A/000/999/5321N00217W005
B)2108121127 C)2110070001
E)INTERMEDIATE HOLDING POINT NA RENAMED NA1
A2905/21
Q)EGTT/QWMLW/IV/BO/AW/000/005/5321N00237W001
B)2108261050 C)2108292200
D)26 1050-1115 1900-2200, 27-29 1900-2200
E)FIREWORK DISPLAY WI 0.5NM RADIUS 532039N 0023713W (DARESBURY,
WARRINGTON, CHESHIRE). FOR INFO 07983 660448. 2021-08-0202/AS5
F)SFC G)500FT AMSL
H5145/21
Q)EGTT/QWALW/IV/M/AW/000/025/5317N00210W002
B)2108281645 C)2108281745
E)AIR DISPLAY/AEROBATICS. WI 1NM RADIUS 531648N 0021021W (WHIRLEY
GROVE, PRESTBURY, CHESHIRE). FOR INFO 07843 498109. 2021-08-0137/AS1
F)SFC G)2500FT AMSL
H5291/21
Q)EGTT/QWMLW/IV/BO/AW/000/009/5320N00215W001
B)2108282100 C)2109042145
D)28 AUG 2100-2145, 04 SEP 2100-2145
E)FIREWORK DISPLAY WI 0.5NM RADIUS 532002N 0021441W (WILMSLOW,
CHESHIRE). FOR INFO 07737 465439. 2021-08-0156/AS5
F)SFC G)850FT AMSL
H4478/21
Q)EGTT/QWMLW/IV/BO/AW/000/005/5320N00224W001
B)2108302030 C)2108302130
E)FIREWORK DISPLAY WI 0.5NM RADIUS 531957N 0022429W (KNUTSFORD,
CHESHIRE). FOR INFO 01565 830155. 2021-08-0606/AS5
F)SFC G)475FT AMSL
H5475/21
Q)EGTT/QWMLW/IV/BO/AW/000/004/5323N00234W001
B)2109031900 C)2109032230
E)FIREWORK DISPLAY WI 0.5NM RADIUS 532308N 0023422W (VICTORIA PARK,
WARRINGTON, CHESHIRE). FOR INFO 07983 660448. 2021-09-0070/AS5
F)SFC G)330FT AMSL
H5148/21
Q)EGTT/QOBCE/IV/M/AE/000/004/5322N00215W001
B)2109060700 C)2109061500
E)LIT CRANE OPR 532137.83N 0021452.87W (1943M, 067 DEG MAG FM
MANCHESTER ARP) MAX HGT 319 FT AMSL, 67 FT AGL
A2998/21
Q)EGTT/QFATT/IV/BO/A/000/999/5321N00217W005
B)2109090000 C)2109222359
E)TRIGGER NOTAM - PERM AIRAC AIP AMDT 09/21 WEF 09 SEP 2021.
FLIGHT PROCEDURES - MANCHESTER LOW LEVEL ROUTE AND FLIGHT MONITORING
CODE (FMC) UPDATED DUE TO CHANGE IN CLASS D VMC MINIMA.
INTRODUCTION OF LLANBEDR DANGER AREA COMPLEX EG D217.
A2702/21
Q)EGTT/QWELW/IV/BO/AW/000/999/5332N00215W002
B)2109112100 C)2109122200
D)11 2100-0400, 12 1900-2200
E)LASER DISPLAY WI 1NM 533213N 0021433W (HEATON PARK, MANCHESTER).
FOR INFO 07713 723196 / 074671 400066. 2021-09-0083/AS2
F)SFC G)UNL
H5243/21
 
Regretfully the airport appears to only be publishing their OANs on an irregular basis. The following are the latest set.

OPERATIONAL ADVICE NOTICE (OAN)

OAN 033/2021 ADVANCED VISUAL DOCKING GUIDANCE SYSTEM (AVDGS) UPGRADES.
OAN REF:‐ 033/2021 DATE OF ISSUE:‐ 20/08/2021 EFFECTIVE DATE:‐ 30/08/2021 EXPIRY DATE:‐ 10/09/2021
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
A two‐week continuation of the programme of work to carry out upgrades to the Advanced Visual Docking Guidance Systems across all three terminals and remote stands.
2.0 PROGRAMME
2.1 The overall programme of work will commence on the Monday 30th August and will be completed by Friday 10th September 2021.
2.2 The daily working hours will be 08:30‐17:00L.
3.0 SCOPE & LOCATION OF WORKS
3.1 The scope of work will entail:
 Installation checks.
 System calibration.
 Set up and configuration.
 Function tests.
 Verification of aircraft STOP position information.
3.2 The continued AVDGS upgrades will be carried out on the following stands:
 Terminal 1: 2, 7 and 9.
 Terminal 2: 107, 110, 208L, 208, 209, 807R, 809, 811, 925 and 927.
 Terminal 3: 41, 43, 47, 49 and 51 – 55R.
4.0 OPERATIONAL IMPLICATIONS
4.1 During the daily working times listed at paragraph 2.2, a series of stand closures will be required. The closures will be agreed each morning in consultation with Airfield Control and the Airfield Duty Manager (ADM).
4.1.1 To limit any operational impact, as far as possible, the stand closures will be coordinated to take advantage of time windows throughout the working day when stands are scheduled to be vacant. However, in some instances there may be a requirement for aircraft towing in order to achieve a vacant stand.
4.2 Safe access to head of stand accommodation will be maintained throughout the programme of work.
4.3 All affected stands will be fully operational outside of the daily working times.
5.0 WORK AREA DEMARCATION
5.1 Work sites on each stand will be demarked by reflective cones.
6.0 LOW VISIBILITY PROCEDURES (LVP)
6.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility.


034/2021 – T2 SWISSPORT DE-ICING TANK REPLACEMENT
OAN REF:- 034/2021 DATE OF ISSUE:- 23/08/2021 EFFECTIVE DATE:- 13/09/2021 EXPIRY DATE:- 17/09/2021
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
1.1 A five-day programme of works to remove an existing bunded de-Icing fluid storage tank at the head of Stand 201 and replace it with a new one in the same location.
2.0 PROGRAMME
2.1 The overall programme of work will commence on Monday 13th September and be completed by Friday 17th September 2021.
2.2 Daily working hours will be 0730 – 1800 local.
2.3 The crane operations will take place on Tuesday 14th and Wednesday 15th September 2021.
3.0 SCOPE & LOCATION OF WORKS
3.1 Overall, the scope of work will involve the following tasks:
• Removal of existing de-icing tank.
• Dismantling and cutting up of the existing de-icing tank.
• Installation of new de-icing tank.
3.2 All work will take place on the head of stand road located directly north of Stand 201.
4.0 OPERATIONAL IMPLICATIONS
4.1 The head of stand road at Stand 201 will be closed to through traffic during the working hours listed at 2.2.
4.2 Access to the airfield red diesel fuelling point and the adjacent de-icing tanks will be maintained by Swissport staff throughout the programme.
4.3 The pedestrian walkway may be obstructed when crane lifting operations are ongoing. In this case, active pedestrian management or a diverted pedestrian walkway will be provided by Swissport.
4.4 The Jet 2 Electric Baggage Tractors (EBTs) situated at the charging points at the head of Stand 201 will be relocated towards the rear of the stand during the crane operations; listed at paragraph 2.3.
4.5 Stand 201 will be closed between the hours of 07:30 and 18:00L on Tuesday 14th and Wednesday 15th September 2021.
4.6 A portion of Equipment Bay 201D, currently occupied by Swissport de-icing vehicles, is required to accommodate a skip for the decommissioning of the existing de-icing tank.
5.0 CONTRACTOR, MANPOWER & EQUIPMENT
5.1 Haven Engineering is the contractor carrying out the replacement on behalf of Swissport.
5.2 Manpower shall be up to a maximum of 7 operatives utilising 1x van, 2x 40t cranes, 1x low loader HGV, 2x skip HGV’s and 1x Mobile Elevated Working Platform (MEWP).
6.0 LOW VISIBILITY PROCEDURES (LVP)
6.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility.
6.2 Work may continue during periods of low visibility at the discretion of the Airfield Duty Manager


OAN 035/2021 RUNWAY 05R-23L MAINTENANCE REPAIRS AND SURVEY.
This OAN replaces OAN 030/2021 with immediate effect. Changes relate to programme dates.
OAN REF:- 035/2021 DATE OF ISSUE:- 23/08/21 EFFECTIVE DATE:- 13/09/21 EXPIRY DATE:- 01/10/21
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
1.1 An additional three weeks of works to complete essential runway maintenance repairs and a walking audit on Runway 05R/23L (R2), taking advantage of the already published closure.
2.0 PROGRAMME
2.1 Work commenced on Monday 26th July and will now be completed by Friday 1st October 2021.
2.2 The planned daily working hours will be 08:00-18:00L.
3.0 SCOPE & LOCATION OF WORKS
3.1 Overall, the scope of work will involve the following tasks:
• Asphalt pavement repairs.
• Maxi-crete repairs.
• Multiple areas of over-banding.
• A walking audit of the runway.
4.0 OPERATIONAL IMPLICATIONS
4.1 Runway Operations
4.1.1 Runway 05L/23R (R1) is the primary runway in use at present and will remain so for the duration of the works.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 In the event of forecast low visibility, the planned work will be cancelled.
 
OAN 036/2021-AIRCRAFT FUEL HYDRANT SYSTEM NIGHT-TIME SHUTDOWN.
OAN REF:‐ 036/2021 DATE OF ISSUE:‐ 26/08/21 EFFECTIVE DATE:‐ 17/09/21
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF

1.0 SUMMARY
1.1 To facilitate the final commissioning of electrical transformers serving the MASHCo Fuel Farm, there will
be a requirement for a temporary night‐time shutdown (circa 1 hour) of the aircraft fuel hydrant system.
The timing of the shutdown will be coordinated to avoid any operational disruption.
2.0 PROGRAMME
2.1 The work will be carried out between 01:00 and 02:00L on the morning of Friday 17th September 2021.
3.0 SCOPE & LOCATION OF WORKS
3.1 The scope of work will be the final commissioning of electrical transformers located at the MASHCo Fuel
Farm.
3.2 All work will take place within the MASHCo Fuel Farm.

4.0 OPERATIONAL IMPLICATIONS
4.1 The aircraft fuel hydrant system shutdown will take place between the hours of 01:00 and 02:00L on the
morning of Friday 17th September 2021.
4.2 The aircraft fuel hydrant system shutdown will affect all hydrant served stands on the airfield.
4.3 The work has been coordinated to avoid operational disruption, and therefore, will not commence until
the final aircraft departure (prior to first wave) requiring hydrant fuelling has been served. In the event
of the final aircraft departure being delayed, the start of work will also be delayed, as required.
4.4 Outside of the above times, the aircraft fuel hydrant system will be operating as normal.

5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 Overall, the work will have no effect on the airport’s ability to operate during periods of low visibility.
5.2 Work may continue during periods of low visibility due to there being no requirement for the works party
to enter the airfield.
 
OAN 037/2021-AIRCRAFT FUEL HYDRANT SYSTEM NIGHT-TIME SHUTDOWNS.

OAN REF:‐ 037/2021 DATE OF ISSUE:‐ 26/08/21 EFFECTIVE DATE:‐ 08/09/21
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF

1.0 SUMMARY
1.1 In addition to the aircraft fuel hydrant system shutdown described within OAN 036/2021, two further
night‐time shutdowns are required to facilitate incoming mains supply servicing enabling work within
the fuel farm switch rooms. The timing of the shutdowns will be coordinated to avoid any operational
disruption.

2.0 PROGRAMME
2.1 The work will be carried out between 01:00 and 04:00L on the mornings of Thursday 9th and Friday 10th
September 2021.

3.0 SCOPE & LOCATION OF WORKS
3.1 The scope of work will be servicing of the incoming electrical mains supply equipment within the fuel
farm switch rooms.
3.1.1 The work described in this OAN is enabling work, prior to that described in OAN 036/2021.
3.2 All work will take place within the MASHCo Fuel Farm.

4.0 OPERATIONAL IMPLICATIONS
4.1 The portion of the aircraft fuel hydrant system serving Terminals 1 and 3 will be shut down between the
hours of 01:00L and 04:00L on the morning of Thursday 9th September.
4.2 The portion of the aircraft fuel hydrant system serving Terminal 2 and the western remote apron will be
shut down between the hours of 01:00 and 04:00L on the morning of Friday 10th September
4.3 The work has been coordinated to avoid operational disruption, and therefore, will not commence until
the final aircraft departure (prior to first wave) requiring hydrant fuelling from the nightly affected
portion of the aircraft fuel hydrant system has been served. In the event of the final aircraft departure
being delayed, the start of work will also be delayed, as required.
4.4 Outside of the aforementioned times, the aircraft fuel hydrant system will be operating as normal.

5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 Overall, the work will have no effect on the airport’s ability to operate during periods of low visibility.
5.2 Work may continue during periods of low visibility due to there being no requirement for the works party
to enter the airfield.
 
OAN 038/2021- TERMINAL 2 BAGGAGE SYSTEM UPGRADE STORAGE COMPOUNDS (MAN-TP PP40).
OAN REF:‐ 038/2021 DATE OF ISSUE:‐ 30/09/21 EFFECTIVE DATE:‐ 11/10/21 EXPIRY DATE:‐ 31/08/22
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF

1.0 SUMMARY
1.1 To facilitate upgrade works on the Terminal 2 baggage system, there will be a requirement for three material storage compounds to be erected on the Terminal 2 apron. The compounds will be located on Stands 207 and 211 and the head of stand road abeam Stand 206. Stands 207 and 211 will be closed H24 whilst the compounds are in‐situ.

2.0 PROGRAMME
2.1 Work to erect the storage compounds will commence on Monday 11th October 2021.
2.2 The three compounds will be in‐situ as follows:
LOCATION COMPOUND ERECTED COMPOUND REMOVED
Stand 207 18/10/21 31/08/22
Stand 211 11/10/21 25/03/22
T2 Head of Stand Road 18/10/21 12/11/21

3.0 SCOPE & LOCATION OF WORKS
3.1 The scope of work will be the erection of three, temporary materials storage compounds on Terminal 2 on Stands 207, 211 and the head of stand road abeam Stand 206.
3.2 Whilst the compounds are in‐situ there will be an ongoing requirement for vehicular airfield access and egress whilst materials are delivered to and removed from site.

4.0 OPERATIONAL IMPLICATIONS
4.1 Stand 207 will be closed H24 from Monday 18th October 2021 until Wednesday 31st August 2022. N.B: The storage compound demarcation will be positioned such that Stands 208 and 208L remain open.
4.2 Stand 211 will be closed H24 from Monday 11th October 2021 until Friday 25th March 2022.
4.3 At various times during the overall programme of works there will be a requirement for short‐term closures of portions of the Terminal 2 head of stand road abeam the materials storage compounds to facilitate transfer of materials to/from the terminal building. Such closures will be no longer than ten minutes each time.
4.4 Whilst the compound is in‐situ on the Terminal 2 head of stand road abeam Stand 206, the available road width will be temporarily reduced. Vehicle drivers must proceed with caution when transiting past the compound.
4.4.1 The pedestrian route adjacent to the compound on the head of stand road will remain open at all times.

5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 Overall, the work will have no effect on the airport’s ability to operate during periods of low visibility.
5.2 All vehicular movements to/from the compounds will be via the apron road system and will be permitted to continue during periods of low visibility.
 
OAN 040/2021 – HIGH VOLTAGE ELECTRICAL MAINTENANCE – SUBSTATION G, TERMINAL 3.
OAN REF:‐ 040/2021 DATE OF ISSUE:‐ 21/10/21 EFFECTIVE DATE:‐ 03/11/21 EXPIRY DATE:‐ 03/11/21
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
On Wednesday 3rd November essential high voltage electrical maintenance work will take place within Substation G serving Terminal 3. The work will require 2x temporary electrical shutdowns of up to 30 minutes duration each. Some apron infrastructure such as Fixed Electrical Ground Power (FEGP), airbridges, and high mast lighting will be temporarily unavailable during the shutdown times.
2.0 SCOPE & LOCATION OF WORKS
2.1 The scope of work will be essential high voltage electrical maintenance work and a temporary switching of the electrical supply onto a generator whilst work is in progress, and back to mains supply upon completion of work.
2.2 All work will be located within Substation G, serving Terminal 3.
3.0 PROGRAMME
3.1 The work will take place on Wednesday 3rd November, with 2x circa 30‐minute electrical shutdowns, coordinated to avoid any operational disruption, taking place as follows:
 Circa 06:00L power will be switched on to generator supply.
 Circa 17:00L power will be switched back to main supply.
4.0 OPERATIONAL IMPLICATIONS
4.1 Whilst the 2x temporary electrical shutdowns take place, as described above, the following apron infrastructure will be unavailable:
 FEGP units on Stands 50‐55.
 Airbridges on Stands 53‐55.
 Stand Number Identification Boards (SNIB) on Stands 50‐55.
 Advanced Surface Movement Guidance & Control System (ASMGCS) antenna ‘RU10’.
 Advanced Visual Docking Guidance (AVDGS) units on Stands 50‐55.
4.2 In advance of the temporary electrical shutdowns, any aircraft connected to and drawing power from the FEGP units on Stands 50‐55 should be disconnected from the FEGP and, if required, re‐connected to a power supply from a mobile GPU.
4.3 Outside of the 2x temporary electrical shutdown periods, all affected apron infrastructure will be operating as normal.
4.4 From Tuesday 2nd November, a generator will be positioned on the Terminal 3 Head of Stand road abeam Stand 54 and will remain in‐situ until completion of works on Wednesday 3rd November.
5.0 LOW VISIBILITY PROCEDURES (LVP)
5.1 The work will have no effect on the airport’s ability to operate during periods of low visibility
 
OAN 041/2021 – STAND 1 CONCRETE PAVEMENT BAY REPLACEMENTS.
OAN REF:‐ 041/2021 DATE OF ISSUE:‐ 21/10/21 EFFECTIVE DATE:‐ 01/11/21 EXPIRY DATE:‐ 02/11/21
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
Stand 1 will be closed for a period of circa 18 hours to facilitate the replacement of 2 x failed concrete pavement bays.
2.0 PROGRAMME
2.1 The programme of work will commence at 12:00L on Monday 1st November, and the stand will be ready to hand back into operation by 06:00L on Tuesday 2nd November 2021.
2.2 The overall programme will consist of circa 12 hours of concrete breakout and reinstatement activities followed by a period of circa 6 hours to allow for concrete curing and work area demarcation removal.
3.0 SCOPE & LOCATION OF WORKS
3.1 The scope of work will be to carry out the replacement of 2 x failed concrete pavement bays on Stand 1. The bays will be replaced using PQX rapid setting concrete.
4.0 OPERATIONAL IMPLICATIONS
4.1 Stand 1 will be closed for a period of circa 18 hours from 12:00L on Monday 1st until 06:00L on Tuesday 2nd November 2021.
5.0 WORK AREA DEMARCATION
5.1 A lit mobile barrier will be placed at the rear of Stand 1 during the closure period.
5.2 The area immediately surrounding the pavement bay replacement works on the closed stand will be demarked by alternate red/white interlocked blocks.
5.2.2 The blocks will be lit by low intensity, red obstacle lighting.
6.0 LOW VISIBILITY PROCEDURES (LVP)
6.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility
 
Landed from Frankfurt last night and noticed work being done on taxiway Alpha (I think) opposite the viewing park…are there any new NOTAM’s available?
 

Remove Advertisements

Subscribe to help support your favourite forum and in return we'll remove all our advertisements. Your contribution will help to pay for things like site maintenance, domain name renewals and annual server charges.



Forums4aiports
Subscribe

Heads Up!

i must be a lunatic. Friday 25th Sept will see me doing a daytrip that involves me leaving my flat in Manchester at 1am and not getting back home until after midnight. All because I'm doing a Loch Ness and Scottish Highlands trip.... out of Glasgow
For some weird reason, my days off work tend to involve being out of my flat by 5am and not getting back until 10pm. Back to work and the regular "fix" of 7.40am to 7.15pm hours
Heatwave Mk2 next week?
Some explosive weather build-ups currently in the North of England. What is it like where you are?
LBA: B737-300 G-GDFK empty down to Paris at 16:15 to operate the return LS268 back to Leeds 20:00 ETA where it will then operate the delayed LS265 to Malaga 20:40ETD