White Heather
Elite Pro-Member
Leedslad, the terminal expansion is still likely to be included in the Masterplan. In fact the airport have done what is required to keep that option open and ensure planning consent is maintained. They have said that when the demand is such that they need it, they will build it. Consequently, no dates are likely unless they are sure that by a given date the extra capacity will be required. Given the relative lack of action in terms of new routes and the money recently spent enabling the car park buses to drop off right outside the current front door, I wouldn't expect that the terminal expansion will start within the next 2 years. But you never know!