Apparently it takes circa 4 months to build and fit out an A321 and as has been reported, there is currently only half a fuselage in Germany. There are also engines (having their own issues), ETOPS, crew visa's and probably a whole host of other stuff to factor in. STN starts in around 3 months.
The programme was always going to be tight but now it seems as if one BHX aircraft at least will be pushed back to Sept and there are rumours that STN may also see the same.
If its 4 months Ray to fit out each A321, they are not going to be able to start any of the schedules on time!!
Aircraft 1 is needed 19th April to start STN-EWR daily
Aircraft 2 is needed 18th May to start CDG-EWR daily
Aircraft 3 is needed 18th May to start BHX-EWR daily
Aircraft 4 is needed 18th May to start STN-BOS & YYZ (4 & 3 weekly)
Aircraft 5 is needed 21st June to start CDG-BOS & YYZ (3 & 4 weekly)
Aircraft 6 is needed 22nd June to start BHX-BOS & YYZ (4 & 3 weekly)
so 12 weeks until aircraft 1 should be entering service, and 3 other aircraft needed in 16 weeks time!
I'm no expert on how long it take to build a A321 and get it ready for service, but I would have thought these dates are impossible to achieve!! Guess only time will tell!