Few little updates.
As referenced above, C3 / 203 is a live stand. This will be followed by C5 / 205 in this coming week.
Trials were completed on 206 this week with help of a Jet2 330. Expect to see something slightly bigger being trialled here in the coming week…
Lots of snagging works that need completing before final handover of the pier - Emirates lounge is still a shell at the moment.
Few things in the design of the pier that have been improved from Pier 1 and then other things that have been badly or not thought through at all.
Reconfiguration works are well underway on stands 29/31/61/62 - once these works are completed the dual taxiway will be able to open.
CCGE29
As referenced above, C3 / 203 is a live stand. This will be followed by C5 / 205 in this coming week.
Trials were completed on 206 this week with help of a Jet2 330. Expect to see something slightly bigger being trialled here in the coming week…
Lots of snagging works that need completing before final handover of the pier - Emirates lounge is still a shell at the moment.
Few things in the design of the pier that have been improved from Pier 1 and then other things that have been badly or not thought through at all.
Reconfiguration works are well underway on stands 29/31/61/62 - once these works are completed the dual taxiway will be able to open.
CCGE29