OAN 115/2018 – MAN-TP MAJOR TAXIWAY SURVEYS (PP04) PHASE 4
THIS OAN REPLACES OAN 96/2018 WITH IMMEDIATE EFFECT OAN REF:‐ 115/2018
DATE OF ISSUE:‐ 14/09/18 EFFECTIVE DATE:‐ 14/11/18 EXPIRY DATE:‐ 21/12/18
1.0 SUMMARY In advance of works to construct the new Taxiway Echo, a fourth phase of surveys will take place which require taxiways and stands to be temporarily closed or restricted until the end of December.
2.0 PROGRAMME
2.1 Overall: 14/11/2018 to 21/12/2018.
2.2 Working days and times: Sunday to Thursday, working hours nights only (20:00‐06:00).
2.3 Works in individual areas are to be determined on a shift‐by‐shift basis within the overall programme. Sufficient taxiways and stands will always be kept available in order to maintain the flying programme.
3.0 SCOPE & LOCATION OF WORKS
3.1 The survey works are required along the length of the proposed Taxiway Echo, from the Western Maintenance Area entrance, extending as far as Stand 72 and across Taxiway November from Stand 69 through Stands 82 and 83 to Stands 210 and 211.
3.1.1 The areas are generally bounded by taxiway strips and the edges of stands.
3.1.2 There is also an area covering the current West Gate security post and RVP West gates. Access to this area is to be agreed with the on‐shift Airfield Security Team Manager at the 1930 shift coordination meeting on a shift by shift basis.
3.2 The scope of works is:
 Ground Penetrating Radar (GPR) survey of all areas.
 Topographical survey
 CCTV inspection of the drainage OPERATIONAL ADVICE NOTICE OPERATIONAL ADVICE NOTICE (OAN) OAN 115/2018 PAGE 2 OF 3  Excavating trial pits to examine ground conditions at depth.
4.0 OPERATIONAL IMPLICATIONS
4.1 Stand Closures and restrictions
4.1.1 Stand closures will be required but will be managed tactically to reduce their impact on the operation.
4.2 Taxiway closures and restrictions
4.2.1 Sections of Taxiways Delta, Quebec and November will be closed individually for several overnight shifts, returning to service by 0600 hours.
4.2.2 Access to stands served from closed taxiways will require a 10‐minute warning to the contractors and be coordinated through Airfield Control.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 The works will have no effect on Low Visibility Procedures. The ADM will determine in conjunction with the ATC Watch Manager whether any works may take place during LVP.
 
OAN 116/ 2018 – MAN -TP PP03 STANDS 216 & 217 PIT, DUCT AND AGL INSTALLATION
EFFECTIVE DATE:- 01/12/18
1.0 SUMMARY
1.1 Installation of ducts and Aeronautical Ground Lights (AGLs) for the relocated Taxilane (ASTL) NovemberAlpha (NA). This work will permanently remove Stands 216L, 217 and 218.
2.0 PROGRAMME
2.1 Saturday 1st December until Friday 25th January 2019.
2.2. The nominal working hours will be: Monday to Friday 0800-1800hrs and Sunday to Thursday 20:00- 06:00hrs local and at other times as required by programme and advised to MAG Operations.
3.0 SCOPE & LOCATION OF WORKS
3.1 All work will be located on Stands 216 and 217. The overall scope of works will involve the following tasks:
3.2 • Closure of Stands 216 and 217.
• Reduction of work compound from TWY Delta to within Stands 216 and 217
• Coring out and installation of AGL.
• Excavation of pits and installation of ducts.
• Removal of painted centrelines, aircraft designators and other related markings.
• Removal of head of stand equipment (FEGP/High mast light/SNIB/Cabin)
• Removal of MAX SPAN 52M, TRP 216 & disused stand designator painted signs on Taxiway Delta.
• Relocation of double white taxiway edge lines to 43.5m from the taxiway centreline.
• Painting in of relocated rear of stand road.
4.0 OPERATIONAL IMPLICATIONS
4.1 Stand Closures
4.1.1 Stand 216L, 217 and 218 are permanently withdrawn from use.
4.2 Taxiway Changes
4.2.1 The double white taxiway edge lines behind Stands 216 to 218 will be relocated to 43.5m from Taxiway Delta centreline and tied in to the double whites behind Stand 215 to return the taxiway to EASA Code E in this section of Delta.
4.3 Airside road traffic
4.3.1 The rear of stand road from 216 to 218 will remain available for access to GSE areas.
4.3.2 The road markings across Taxiway Delta from Stand 215 to 245 will be permanently removed. If weather delays the removal of the paint markings then red and white water filled blocks will be used to close the entrance to the road. NB. The removal and addition of paint markings is entirely weather dependant; therefore, the programme may slip. This may delay the opening of Taxiway November-Alpha in its new location. OAN 118 – 2018 refers
4.4 Ground Service Equipment (GSE) parking
4.4.1 GSE parking areas at Stands 216 and 217 will be withdrawn from use. Allocated users will be advised of changes to their GSE parking areas individually by the Project Manager.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 The works will have no effect on Low Visibility Procedures.
 
OAN 117 / 2018 – MAN -TP FUEL HYDRANT - PIER 1
OAN REF:- 117/2018 DATE OF ISSUE:- 16/11/18 EFFECTIVE DATE:- 01/12/18
1.0 SUMMARY
1.1 As part of the Manchester Transformation Programme, Manchester Airport Storage and Hydrant Company Limited (MASHCo), is required to install new main header pipework and hydrant pots from Stand 86 to 218 to supply fuel to the new piers.
2.0 PROGRAMME
2.1 Overall: Saturday 1st December 2018 until Friday 1 st March 2019.
2.2 The nominal working hours will be: Monday to Friday 0800-1800hrs and Sunday to Thursday 20:00- 06:00hrs local and at other times as required by programme and advised to MAG Operations.
3.0 SCOPE & LOCATION OF WORKS
3.1 Works will be located on stands 86, 247 & 218 and Taxiway Delta.
3.2 Overall scope of works as follows for each of the above located work areas:
• Enclose the works areas with Heras fence and water filled red and white blocks.
• Creation of welfare area within compound.
• Excavation of trench from Taxiway November, across Stand 86 and Twy Delta to Stand 218.
• Installation of pipework and hydrant pots.
• Radiography inspection of welded joints.
• Cathodic Protection installation.
• Backfilling and concrete reinstatement.
• Pressure test carried out with water.
• Connection to the live fuel hydrant system.
4.0 OPERATIONAL IMPLICATIONS
4.1 Stand Closures
4.1.1 Stands 86, 247 and 218 are permanently withdrawn from service.
4.2 Taxiway Closures & Restrictions
4.2.1 Taxiway Delta will be closed abeam Stand 217/218 clearway.
4.2.2 A small section of the MASHCO excavation is 37m from the Taxiway November (N) centreline. This infringes a Code E taxilane (ASTL) by 3m and will be left in a sterile condition and delineated with red and white sleepers lit with low intensity red obstacle lights until its completion. No works in this section of the excavation unless prior ADM approval has been received and TWY N is closed.
4.3 GSE Areas
4.3.1 Ground Service Equipment (GSE) will be relocated to available space on Stands 86, 247 and 218.
4.3.2 The Project Manager will contact all companies affected ahead of the stand closures to arrange for any GSE/equipment to be relocated.
4.4 Aircraft Fuel Hydrants
4.4.1 The connection of the new pipe work to the live fuel hydrant system will not affect any live stands.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 The work has no effect on existing Low Visibility Procedures.
 
In OAN 116/2018 there is reference to the OAN118/2018 and the relocation of taxiway November Alpha.

As at today this new notice has not yet been issued. OAN121/2018 has been posted however as it refers to internal SMS messages I will not be copying it to this thread.

When OAN118 through to 120/2018 are published I'll issue an update on here.
 
OAN 119/2018 – MAN-TP DRAINAGE SURVEY
OAN REF:‐ 119/2018 DATE OF ISSUE:‐ 16/11/18 EFFECTIVE DATE:‐ 26/11/18 EXPIRY DATE:‐ 30/11/18
1.0 SUMMARY
1.1 Survey of the drains in the vicinity of the Stand 205 equipment bay and the Stand 206 head of stand road which will require the closure of the stand 206 head of stand road for 1 night.
2.0 PROGRAMME
2.1 A two‐day programme (one night shift and one day shift) to open up 2 x pit lids and survey the drains. Security oversight will be required when the lids are open as the drains run to landside areas.
2.2 Work areas by date:
 Monday 26th November 2018: Opening and surveying 1 x pit in the Stand 205 equipment bay. Working hours 08:00‐16:00
 Tuesday 27th November 2018: Opening and surveying 1 x pit on the T2 head of stand road abeam Stand 206, closing the road and Gate 400 arrivals for the duration of the shift. Working hours 21:00‐05:00 Note: In the event of rain this survey may have to be postponed due to high water levels in the drains. In this event the 28th to the 30th of November are contingency days.
3.0 SCOPE & LOCATION OF WORKS
3.1 The survey works are required in the following locations:
 Area 1: Stand 205 equipment bay.
 Area 2: Road 206 head of stand road.
4.0 OPERATIONAL IMPLICATIONS
4.1 Area 1:
4.1.1 For the work in Area 1 (205 GSE bay) a small amount of equipment will have to be removed or rejigged by Swissport to enable to the set‐up of a 5m x 5m Heras fence compound.
4.1.2 It is the responsibility of the MAN‐TP Arcadis Project Manager to arrange access to the stand 205 equipment bay with Swissport and the temporary removal of any equipment if required.
4.2 Area 2:
4.2.1 For the work in Area 2, a small portion of the HOS road abeam Stand 206 must be closed which could impede turn around activity for wide body aircraft on Stand 206C (notably towing weldworks to and from the forward hold). Stand 206L will be available as usual. 4.2.2 Gate 400 will be unavailable whilst the head of stand road is closed. All remote international arrivals to go into a pepper pot (to be coordinated with airfield control).
4.2.3 TDM/CSTM to ensure that Customer Services and Security are in attendance at pepper pots to facilitate arrivals.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 This survey work has of effect on the airfields ability to operate in low visibility.
 
OAN 118/ 2018 – MAN-TP AIRSIDE CONSTRUCTION PP03 (4C)
OAN REF:- 118/2018 DATE OF ISSUE:- 20/11/18 EFFECTIVE DATE:- 05/12/18 EXPIRY DATE:- 26/07/19
1.0 SUMMARY
1.1 Works are continuing airside to construct new aprons and taxi-lanes and to reconfigure existing airside areas. Taxiway November-Alpha will be relocated 82 m north of its existing location and excavations and installations will take place at its old location to form the new Terminal 2, Pier 2 Remote Stands.
2.0 PROGRAMME
2.1 Overall: Wednesday 5th December 2018 to Friday 26th July 2019.
2.2 Working hours
2.2.1 Nominal working hours within main site will be Monday to Friday 08:00-18:00 and Sunday to Thursday 20:00-06:00hrs local; at other times as required by programme and advised to MAG Operations
2.2.2 Working hours on Taxiways November-Alpha and Delta will be Sunday to Thursday 22:00-06:00hrs local.
2.2.3 See attached drawing for exact locations of day and night time working.
3.0 SCOPE & LOCATION OF WORKS
3.1 The main works site is at the north-western end of the existing apron, encompassing the former Taxiway November-Alpha (NA) and the remaining grass areas either side.
3.2 The night-working area will encompass the relocated Taxiway NA and the cul-de-sac section of Taxiway Delta (D).
3.3 The scope of works is:
• Excavation of grass areas and laying of new concrete pavement.
• Installation of electrical pit and duct lines.
• Installation of aviation fuel hydrant mains.
• Installation of aeronautical ground lighting (AGL).
• Removal and application of surface markings.
• Saw cutting of new concrete pavement
4.0 OPERATIONAL IMPLICATIONS
4.1 Stand Restrictions
4.1.1 If any aircraft are required to park or be removed from Stand 243 whilst the night time works are ongoing, they must do so under tow. An ASCO will be dispatched to oversee this procedure to ensure that no plant/vehicles are obstructing the stand and that the red hatched area next to the starboard wing is clear.
4.2 Taxiway Closures and Restrictions
4.2.1 Taxiway NA, at its new location, will be closed 2200-0600hrs local, Sunday to Thursday.
4.2.2 Taxiways NA & D will be available by day 0600-2200 hours Local time. There will be an area of excavations within the Code E (B747 / A330) taxiway strip of taxiway D on the northern side. The works will not be active during the day time when NA and D are open to aircraft operations. The low-level blocks surrounding the excavation will be placed at 20 metres from the centreline of D (outside the graded portion of the strip). Wingtips of aircraft using D will overhang the excavated area, which will be cleared of any upstanding objects or loose materials.
4.2.3 The stub of Taxiway D, abeam Stand 243, will be closed to aircraft from 22:00-06:00hrs local Sunday to Thursday.
4.2.4 The Aeronautical Ground Lights (AGLs) along Taxiway November from abeam Stand 71 to Stands 901/903, along the relocated NA and around the radii on to Taxiway D to abeam Stand 243 will remain unlit H24 throughout this works programme. Airfield Operations will provide a Follow Me vehicle during the hours of darkness and low visibility operations.
4.3 Pushback Procedures
4.3.1 Pushback from Stand 243 is aircraft nose wheel abeam Stand 241 centreline facing the runways.
4.3.2 The above pushback procedure is listed in the MA Aircraft Pushback Procedures, Revision Xray which was published on 14th November 2018.
4.3.3 Between 22:00 and 06:00 hours, when Taxiway D is closed from abeam Stand 243, pushbacks from Stands 211, 237, 239, 241 and 243 will be aircraft nose wheel abeam Stand 237 centreline facing the runways prior to engine start. N.B. Airfield Ops must advise works party to move aside and temporarily remove closure barriers prior to any pushback taking place.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 The works will have no effect on Low Visibility Procedures. The night-time closure of Taxiway NA will be cancelled in the event of LVP. 5.2 Work may continue within the main site during periods of low visibility at the ADM’s discretion.


View attachment 11396
View attachment 11397
 
OAN 122 / 2018 – FIXED ELECTRICAL GROUND POWER RENEWALS ON STANDS 72 AND 69
OAN REF:- 122/2018 DATE OF ISSUE:- 22/11/2018 EFFECTIVE DATE:- 03/12/18 EXPIRY DATE:- 17/12/18
1.0 SUMMARY Fixed Electrical Ground Power (FEGP) unit renewals on Stands 72 and 69. Both stands are to remain open but with limited FEGP availability whilst work is in progress.
2.0 PROGRAMME
2.1 Overall works programme starting Monday 3rd December 2018 for a period of 2 weeks until Monday 17th December 2018. Individual stand works programmes as follows:
2.2 • Stand 69 Monday 3rd December 2018 – Friday 7th December 2018.
2.3 • Stand 72 Monday 10th December 2018 – Friday 14th December 2018.
2.4 The works shall be conducted Monday-Friday during daylight hours.
3.0 SCOPE & LOCATION
3.1 Fixed Electrical Ground Power (FEGP) replacements are required on Stands 69 and 72.
3.2 The works will incorporate the following tasks:
• Removal of existing FEGP unit
• Installation of new FEGP unit • Commissioning works
3.3 Works shall take place at the head of each stand, and not affect the stand footprint or availability.
4.0 OPERATIONAL IMPLICATIONS
4.1 Stands 69 and 72 shall have no FEGP functionality between the dates outlined in paragraphs 2.2 and 2.3. During these periods mobile Ground Power Units (GPU’s) shall be required for electrical power on each stand.
5.0 LOW VISIBILITY OPERATIONS
5.1The works shall have no implications on the Airport’s ability to operate during periods of low visibility.
 
OAN 123/2018 – MAN-TP PP04 CONSTRUCTION OF NEW TAXIWAY DELTA PHASE D2
OAN REF:- 123/2018 DATE OF ISSUE:- 26/11/18 EFFECTIVE DATE:- 10/12/18 EXPIRY DATE:- 31/05/19
1.0 SUMMARY
1.1 A rolling programme of up to 6 months work to install pits and ducts in phase D2 of the new taxiway Delta, commencing on Stand 62 and finishing on Stand 70.
2.0 PROGRAMME
2.1 Overall: Monday 10th December 2018 to Friday 31st May 2019.
2.2 Nominal working hours within main site will be Monday to Friday 08:00-18:00 and Sunday to Thursday 20:00-06:00hrs local; at other times as required by programme and advised to MAG Operations
2.3 The work will be carried out in six phases; each approximately 5 weeks in duration
2.3.1 Nominal phase dates are:
View attachment 11488
3.0 SCOPE & LOCATION OF WORKS
3.1 Work will start on Stands 62 and 63 and will be located within an enclosed and demarked work area.
3.2 The overall scope of works will encompass the following:
• Site establishment for each phase with full height, lit, Heras fencing and red/white baseboards.
• Excavation and installation of pits and ducts.
4.0 OPERATIONAL IMPLICATIONS
4.1 Taxiway Closures
4.1.1 Taxiway Quebec will be closed from 10th December 2018 and remains closed throughout phases 1 & 2.
4.2 Stand Restrictions
4.2.1 The work commences with phase one which will close Stands 62 and 63. As each phase of works is completed it will move on to the next phase encompassing the next two stands until it completes on Stand 70. The fencing from Stand 62 will be relocated to Stand 64 and Stand 62 will reopen; then from Stand 63 to Stand 65 etc so that the next phase compound is established. See paragraph 2.3.1 for nominal dates and stands.
4.3 Road restrictions
4.3.1 The road from West Gate across Taxiway Delta to Stand 31 will be maintained always throughout Phase 2; though there will be a need to divert it slightly to access the existing pit in the road.
4.3.2 The access gate and road for the emergency Rendezvous Point (RVP) West will be maintained always throughout the works.
4.4 Facilities Restrictions
4.4.1 Access to the Thomas Cook hangar via Stand 63 will not be available from Monday 10th December until the completion of phase 1 on or around 14th January 2019.
4.4.2 The Unit Load Devices (ULDs) racking system on Stands 66 to 70 will remain accessible throughout the works.
4.5 Ground Service Equipment (GSE) and Parking Areas
4.5.1 Access to GSE areas at the head of each stand will be maintained throughout the works.
4.5.2 The project manager will advise the fuel companies if any hydrant carts need to be displaced onto Stand 65 during Phase 3. See attached drawing.
5.0 LOW VISIBILITY PROCEDURES (LVP)
5.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility.

View attachment 11489
 
OAN 124 / 2018 – MAN-TP CABLE INSTALLATION (PP16)
OAN REF:- 124/2018 DATE OF ISSUE:- 27/11/18 EFFECTIVE DATE:- 03/12/18 EXPIRY DATE:- 07/12/18
1.0 SUMMARY
1.1 A three-night programme of works to install fibre optic cables between R Sub at West Gate and X Sub at C Pier. This will involve accessing the existing pit and ducted system between the two locations to carry out rod and roping prior to the installation of new cabling. 2.0 PROGRAMME
2.1 Monday 3rd December to Wednesday 5th December 2018, with Thursday 6th December as a contingency night.
2.2 Nightly working hours will be 22:00 to 05:00hrs local unless otherwise agreed by the Airfield Duty Manager (ADM).
3.0 SCOPE & LOCATION OF WORKS
3.1 The works will originate at R Sub, cross taxiway November to the grassed area beside Taxiway Papa, then across Taxiway Delta to Stand 31 and terminate at X Sub. See attached drawings.
3.2 Overall the work comprises of the following:
• The removal and replacement of existing cable chamber lids, entry, working within and exit of the chambers.
• Jet wash/cleaning of ducts.
• The proving of the connecting duct systems using a rod system.
• The installation of draw ropes from pit to pit.
• Cable installation.
4.0 OPERATIONAL IMPLICATIONS
View attachment 11490
4.2 Contractors are able to vacate the area with a 20-minute notice period for taxiing aircraft or aircraft under tow.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 In the event of forecast low visibility, the planned night works will be cancelled.
5.2 In the event of un-forecasted LVP conditions prevailing during periods of working the works party must cease work and vacate the airfield.
5.2.1 The works party will require 30 minutes to reinstate the pits, remove their equipment and vacate the airfield.
View attachment 11491View attachment 11492
 
I forgot to share this OAN- which I appreciate is now out of date - but it gives continuity of numbers:

OAN 125/2018 – SCHEDULED RUNWAY 05L-23R NIGHT-TIME MAINTENANCE.
OAN REF:‐ 125/2018 DATE OF ISSUE:‐ 27/11/18 EFFECTIVE DATE:‐ 04/12/18 EXPIRY DATE:‐ 07/12/18
1.0 SUMMARY
1.1 Runway 05L‐23R will be closed for three consecutive nights in early December 2018 to allow for essential maintenance works on the runway and within its associated strip. All flight operations will take place on Runway 05R‐23L whilst work is in progress.
2.0 PROGRAMME
2.1 Work will take place on the nights of Tuesday 4th to Thursday 6th December 2018, inclusive.
2.2 The nightly working hours will be 22:30 – 06:00L.
3.0 SCOPE & LOCATION OF WORKS
3.1  Drainage CCTV surveys along Runway 05L‐23R between Links Alpha and Foxtrot.
 Routine maintenance tasks including maintenance of painted runway markings, runway surface friction assessments and aeronautical ground lighting (AGL) repairs/ replacements and bolt inspections.
 Replacement of 1 x concrete pavement bay on Taxiway Bravo, west of Intermediate Holding Point (IHP) B2.
 Asphalt pavement repairs on Taxiway Alpha between IHPs A2 and A3.
 Operation of a lit crane within the MAN‐TP Taxiway Echo construction site, located on Taxiways Bravo and Kilo (Tall Equipment Permit TE‐00254 refers).
 Ground Penetrating Radar (GPR) survey work, south of Runway 05L‐23R within the Runway 23R ILS Glideslope Critical Area (MWB 30/2018 refers).
4.0 OPERATIONAL IMPLICATIONS
4.1 Runway Operations
4.1.1 During the Runway 05L‐23R closure periods (22:30‐06:00L) all flight operations will take place on Runway 05R‐23L.
4.2 Taxiway Restrictions
4.2.1 Taxiway Alpha, between IHPs A2 and A3 will be closed each night that work takes place.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 In the event of forecast low visibility, the night works will be cancelled and Runway 05L‐23R will remain open.
5.2 In the event of un‐forecast reduced visibility conditions (minima of IRVR 800m or Cloud Ceiling 300ft) during the Runway 05L‐23R closure period when work has begun, the aerodrome will close to flight operations whilst the runway is recovered. An ‘AD Closed’ NOTAM will be issued in such circumstances.
 
OAN 127/2018 – INSTALLATION OF AIRCRAFT FUEL HYDRANTS ON STANDS 57 & 58.
OAN REF:‐ 127/2018 DATE OF ISSUE:‐ 07/12/18 EFFECTIVE DATE:‐ 07/01/19 EXPIRY DATE:‐ 29/04/19
1.0 SUMMARY
1.1 A programme of up to four months work to install new aircraft fuel hydrants on Stands 57 and 58. For the duration of the works programme, Stands 55R, 57 and 58 will be closed. Additionally, a portion of the apron road system linking the Terminal 3 head and rear of stands roads, adjacent to Stand 55 will be diverted through a demarked route.
2.0 PROGRAMME
2.1 The overall programme of work will commence on Monday 7th January 2019.
2.2 The scheduled works completion date is Monday 29th April 2019.
2.3 The work will take place seven days a week, with daily working hours of 07:00 – 18:00L.
3.0 SCOPE & LOCATION OF WORKS
3.1 The overall scope of work will be the installation of new pipework from Valve Chamber VC‐G (located at the head of Stand 55R) to serve Stands 57 and 58, followed by the installation of new aircraft fuel hydrants.
3.2 All work will be located within a demarked work area located across Stands 57, 58 and partially within Stand 55R. See attached drawing.
4.0 OPERATIONAL IMPLICATIONS
4.1 Stand Closures
4.1.1 Stands 55R, 57 and 58 will be closed H24 for the duration of the works programme.
4.1.2 Stands 55 (main centreline) and 55L will be unaffected by the works.
4.2 Parking of Ground Service Equipment
4.2.1 Whilst work is in progress, it will not be possible to access Equipment Bays 55, 55C, 57D or 58B. Any vehicles/equipment that usually park in these bays will be temporarily relocated to an area at the rear of the closed Stand 57.
4.2.2 Access to the temporary equipment parking area will be via the apron road system and the Interstand Clearway to the east of Stand 58.
4.2.3 Those parties required to temporarily relocate parked/stored equipment will be notified separately by Airfield Operations.
4.3 Apron Road System
4.3.1 A portion of the apron road system, immediately to the east of Stand 55 will be diverted through a demarked route (along the closed Stand 55R) for the duration of the works.
4.4 Aircraft Fuel Hydrant System
4.4.1 As the programme of work progresses, there will be a requirement for an overnight aircraft fuel hydrant shutdown whilst the new hydrants are integrated into the overall hydrant system.
4.4.2 Any fuel hydrant shutdowns will be subject of a separate OAN, which will be issued nearer the time (likely to be during March 2019). 4.5 Overnight Storage of Aircraft on Taxiway Golf
4.5.1 Whilst Stands 57 and 58 are closed it will be possible to park up to 3 x aircraft overnight on Taxiway Golf (east of Intermediate Holding Point G3).
4.5.2 The maximum permitted aircraft size for overnight parking on the taxiway will be B737‐800.
4.5.3 Aircraft parking on Taxiway Golf will be for towed aircraft movements only, under direction from Airfield Operations, and at the discretion of the Airfield Duty Manager.
4.5.4 The attached overall works area drawing drawing shows indicative aircraft parking positions on Taxiway Golf.
5.0 LOW VISIBILITY PROCEDURES (LVP)
5.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility.


View attachment 11585
 
Since I've not seen an OAN having been issued for this change, although OAN 126/2018 is currently missing, I thought I would include details from the relevant NOTAM

Q) EGTT/QMXCL/IV/M/A/000/999/5321N00217W005
B) FROM: 18/12/10 16:00C) TO: 19/03/10 06:00
E) TWY NA HAS RELOCATED 82M NORTH OF OLD LOCATION. TWY IS UNLIT. FOLLOW
ME PROVIDED HN AND DURING LOW VIS OPS

My understanding of this change is that the airport is temporarily using the new Pier One taxiway Kilo but under the old taxiway name.

Any thoughts from anyone else?
 
Hi Scottie

It is OAN 118.

I agree this seems to be the new Kilo or at least most of it but they have clearly decided to keep November Alpha until either it is complete or until they rename all the taxiways. It will become operational between Delta and November within the next month so they can start on the remotes for Pier 2
 
Thanks Comet. Roverman on Pprune has confirmed our thoughts although he says that it will remain as November Alpha until around early 2020 before being given its new designation of Kilo.
 
Screenshot-139.png
 
OAN 129/2018 – OVERNIGHT PAVEMENT REPAIRS.
OAN REF:‐ 129/2018 DATE OF ISSUE:‐ 17/12/18 EFFECTIVE DATE:‐ 13/01/19 EXPIRY DATE:‐ 25/01/19
1.0 SUMMARY
A programme of ten working night shifts to complete multiple airfield pavement repairs on Taxiways Juliet‐Echo, Juliet‐Foxtrot, Juliet, Bravo and Alpha. The work will require a series of localised, overnight taxiway closures, and in some instances, there will be a requirement for night‐stopping aircraft to be parked on stands before pavement repair work takes place.
2.0 PROGRAMME
2.1 The overall programme of work will commence on the night of Sunday 13th January 2019.
2.2 The work is scheduled to be completed by the morning of Friday 25th January 2019.
2.3 Overall, the work will take place Sunday to Thursday nights (inclusive) each week, with nightly working hours of 22:30 – 06:00L.
3.0 SCOPE & LOCATION OF WORKS
3.1 The required working locations will be as follows;
 Sunday 13th and Monday 14th January – Taxiway Juliet‐Echo.
 Tuesday 15th – Thursday 17th January – Taxiways Juliet (J3 and J4) and Taxiway Alpha (A1).
 Sunday 20th and Monday 21st January – Taxiway Juliet‐Foxtrot.
 Tuesday 22nd – Thursday 24th January – Taxiway Bravo (B5‐B6).
3.2 The scope of work will involve a variety of repair methods including;
 PQX pavement bay replacement.
 Maxicrete repairs.
 Fastpatch and sub‐surface grout injection.
 Asphalt inlay repairs
 Sealing of pavement cracks.
4.0 OPERATIONAL IMPLICATIONS
4.1 Taxiway Closures
4.1.1 The following schedule of nightly (22:30‐06:00L) taxiway closures will be required to facilitate the work;
Taxiway Juliet‐Echo Closed Sunday 13th & Monday 14th January
Taxiway Juliet‐Foxtrot Closed Sunday 20th & Monday 21st January
Taxiway Bravo (B5‐B6) Closed Tuesday 22nd – Thursday 24th January
4.1.2 The required pavement repair work on Taxiways Juliet (J3‐J4) and Alpha (A1) will be carried out concurrent with a scheduled night‐time maintenance closure of Runway 05L‐23R, therefore no operational implications are anticipated.
4.1.3 All the aforementioned taxiways will be fully operational outside of the nightly working times.
4.2 Stand Restrictions
4.2.1 Prior to works starting on Taxiway Juliet‐Echo, night‐stopping aircraft are to be parked on Stands 1, 5, 7, 9, 11, 15 and 16.
4.2.1.1 As part of the night‐time works on Taxiway Juliet‐Echo, the replacement of 1 x failed pavement bay at the rear of Stand 16 will be carried out. As such, Stand 16 will be closed overnight on either Sunday 13th or Monday 14th January.
4.2.2 Prior to works starting on Taxiway Juliet‐Foxtrot, night‐stopping aircraft are to be parked on Stands 42, 43 and 44.
4.2.3 The works on Taxiway Bravo (B5‐B6) will be managed such that aircraft access to either Taxiway Juliet‐ Echo or Juliet‐Foxtrot, and the stands served by those taxiways will be retained whilst work is in progress.
4.3 Aircraft Push-back Manoeuvres
4.3.1 Whilst night‐time work is in progress on Taxiway Juliet‐Echo, aircraft push-backs from Stands 1, 5, 7, 9, 11, 15, 16, 17, 18 and 41 will not be possible.
4.3.2 Whilst night‐time work is in progress on Taxiway Juliet‐Foxtrot, aircraft push-backs from Stands 17, 18, 41, 42, 43 and 44 will not be possible.
4.3.3 Whilst night‐time work is on progress on Taxiway Bravo (east of B6) aircraft push-backs from Stand 44 will not be possible. Additionally, non‐standard aircraft push-backs will be required for Stands 17, 18, 41, 42 and 43, with all aircraft being pushed back to face the terminal building, before taxiing out via Taxiway Juliet‐Echo.
4.3.4 Whilst night‐time work is in progress on Taxiway Bravo (west of B6) aircraft push-backs will not be possible from Stands 11 and 15. Additionally, non‐standard aircraft push-backs will be required for Stands 1, 5, 7, 9, 11 and 16, with all aircraft being pushed back to face the terminal building, before taxiing out via Taxiway Juliet‐Foxtrot.
4.3.5 Dependant on overall progress during each phase of work, it may be possible for some night‐time aircraft pushback limitations to be lifted. This will be determined tactically on a nightly basis by the Airfield Duty Manager.
4.5 Apron Road System
4.5.1 As part of the scope of works for Taxiway Juliet‐Echo, there will be 2 x asphalt patch repairs carried out within the apron road system at the rear of Stands 7 and 9. Local traffic management will be in place to guide vehicles around the areas of pavement repair. 5.0 LOW VISIBILITY PROCEDURES (LVP)
5.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility.
5.2 In the event of forecast low visibility, the planned night works will be cancelled.
6.0 FURTHER INFORMATION
6.1 A NOTAM(s) promulgating significant operational detail will be issued prior to the start of works.
 
OAN 128/2018 – MAN-TP PP04. CONTINUATION OF NEW TAXIWAY ECHO CONSTRUCTION WORKS AREA & TAXIWAY BRAVO (B3) PAVEMENT BAY REPLACEMENTS
OAN REF:- 128/2018 DATE OF ISSUE:- 18/12/18 EFFECTIVE DATE:- 06/01/19 EXPIRY DATE:- 29/03/19
1.0 SUMMARY
1.1 A programme of up to twelve weeks work to reconstruct concrete pavement bays on a section of Taxiway Bravo at Intermediate Holding Point (IHP) B3 to bring it up to the standard of the new Taxiway Echo. Furthermore, adjacent pavement construction works, as part of MAN-TP, will continue on a portion of Taxiways Kilo and Bravo. Whilst work is in progress there will be H24 closures of portions of Taxiways Bravo, Kilo and Charlie.
2.0 PROGRAMME
2.1 The overall programme of work will commence on the night of Sunday 6th January 2019.
2.2 Overall, the work will be completed by the morning of Friday 29th March 2019.
2.3 Overall, the work will take place Sunday to Thursday nights (inclusive) each week, with nightly working hours of 20:00 – 06:00L.
2.4 The pavement bay replacement work on Taxiway Bravo will consist of 10 weeks of construction work, followed by a period of up to two weeks to allow for concrete curing.
3.0 SCOPE & LOCATION OF WORKS
3.1 The overall scope and location of work will be as follows;
• Replacement of 40 x concrete pavement bays on Taxiway Bravo, at IHP B3.
• Continuation of MAN-TP taxiway construction works on Taxiway Kilo.
4.0 OPERATIONAL IMPLICATIONS 4.1 Taxiway Closures
4.1.1 The following taxiway closures will be in effect H24 from 06:00L on Friday 21st December until 06:00L on the morning of Friday 29TH March 2019;
• Taxiway Bravo between IHPs B2 and B3.
• Taxiway Charlie at IHP C1.
• Taxiway Kilo at IHP K4.
4.2 Northside Taxiways
- Aircraft Manoeuvring Restrictions
4.2.1 For the duration of the works, aircraft will be routed around the works area using a combination of Taxiway Alpha (via IHP A4), Taxiway Charlie (via IHP C2) and Taxiway Delta (via IHP D3), as required.
4.2.2 Flight crews should be aware that the turn between IHPs C2 and D3 has an unlit painted taxiway centreline and blue taxiway edge lighting.
4.2.3 Furthermore, the turn between IHPs C2 and D3 is restricted in terms of permitted aircraft size, as follows;
• C2 to D3 (right turn) – Maximum A330-300.
• D3 to C2 (left turn) – Maximum B757-300.
4.2.4 Aircraft larger than those specified above that cannot taxi past the works area using the turn between IHPs C2 and D3 will be required to either;
• Take a diverted taxiway route via Taxiways Lima and Delta.
• Backtrack Runway 05L-23R, as directed by ATC.
4.2.5 Taxiway Bravo between IHP B4 and IHP B5 will be downgraded to a Code E Taxilane for the duration of the works.
4.2.6 Due to the requirement for mustering of works site traffic, Taxiway Bravo, between IHPs B4 and B5 will be restricted to a maximum of ICAO Code C aircraft types (B737/A321) each night that work takes place. The taxiway will be returned to ICAO Code E (B747/B777) capability upon the completion of works each morning. The fixed melba logs positioned at 26m from Taxiway Bravo centreline, delineating the muster point, and the portable blast screens will remain in situ throughout the works.
4.3 Implications for manoeuvring of ICAO Code F (A380) Aircraft
4.3.1 For the duration of the works, Taxiway Alpha, via IHP A4, will be available for use by ICAO Code F (A380) aircraft. The route provides an ICAO Code F ASTL strip width of 47.5m.
4.3.2 A380 aircraft, taxiing inbound following a Runway 23R arrival will be met at IHP A3 by an Airfield Operations Follow-Me vehicle, and guided along Taxiway Alpha via IHP A4, thence onwards through Taxiway Charlie via IHP C2 (for docking on Stand 12).
4.3.3 A380 flight crews may require the use of judgemental oversteer techniques due to pavement to main gear clearance dropping to a minimum of 2m along a portion of the sweeping turn to the west of IHP A4.
4.3.4 For A380 aircraft departing from Stand 12, a choice of two standard pushback manoeuvres will be introduced, as follows;
• Push tail towards IHP D4, pull forward to TRP 12, facing runways. Engine start at TRP. or
• Push back onto Taxiway Delta through IHP D4. Aircraft nose-wheel abeam Stand 61L centreline facing IHP A5.
4.3.5 The choice of pushback manoeuvre will be selected tactically by ATC.
4.3.6 The choice of A380 pushback procedures are described within Manchester Airport Aircraft Pushback Procedures Revision X-Ray and are depicted within this document.
4.3.7 When pushed back to abeam Stand 61L, for a Runway 05L departure, after tug release, the aircraft will be instructed to taxi straight-on along Taxiway Alpha, through IHP A5.
4.3.8 When taxiing outbound to Runway 05L via Taxiway Alpha, an Airfield Operations Follow-Me vehicle will be positioned at IHP A5 and will guide the aircraft along Taxiway Alpha. 4.3.9 Standard taxi routes following a Runway 05L or 05R arrival, and for a Runway 23L or 23R departure will be unaffected.
4.4 Aircraft Engine Testing
4.4.1 The Engine Test Bay will be available for use throughout the programme of works, with some limitations, as described below.
4.4.2 Due to the interface between the Engine Test Bay and the adjacent (active) Taxiway Alpha, there may be timing restrictions put in place for Engine Test Bay bookings for the following aircraft types;
• B747, A340-500, A350-900.
4.4.3 When the above aircraft are parked within the Engine Test Bay, Taxiway Alpha will be closed.
4.4.4 Aircraft up to a maximum size of A330-300/ B777-200 may be parked in the Engine Test Bay whilst Taxiway Alpha is operational, this includes the use of Taxiway Alpha by ICAO Code F (A380) aircraft.
4.4.5 The designated open-field engine testing location on Taxiway Kilo will be unavailable for the duration of the works. Depending on the prevailing runway operating mode, open-field testing locations will be tactically determined by the Airfield Duty Manager and will consider any operational impact such engine testing may have on the airfield.
4.4.6 Further information regarding aircraft engine testing can be obtained from the Airfield Duty Manager. NB: Due to local authority agreements and government planning conditions, open-field engine tests are subject to extensive restrictions and therefore significant delays to the commencement of engine tests on the open airfield may occur during this phase of development work.
5.0 LOW VISIBILITY PROCEDURES (LVP)
5.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility.
6.0 FURTHER INFORMATION
6.1 A NOTAM(s) promulgating significant operational detail will be issued prior to the start of works. An updated AIP Supplement will be published on 17th January 2019.

View attachment 11697
 
OAN 129/2018 – OVERNIGHT PAVEMENT REPAIRS.
OAN REF:‐ 129/2018 DATE OF ISSUE:‐ 17/12/18 EFFECTIVE DATE:‐ 13/01/19 EXPIRY DATE:‐ 25/01/19
1.0 SUMMARY
A programme of ten working night shifts to complete multiple airfield pavement repairs on Taxiways Juliet‐Echo, Juliet‐Foxtrot, Juliet, Bravo and Alpha. The work will require a series of localised, overnight taxiway closures, and in some instances, there will be a requirement for night‐stopping aircraft to be parked on stands before pavement repair work takes place.
2.0 PROGRAMME
2.1 The overall programme of work will commence on the night of Sunday 13th January 2019.
2.2 The work is scheduled to be completed by the morning of Friday 25th January 2019.
2.3 Overall, the work will take place Sunday to Thursday nights (inclusive) each week, with nightly working hours of 22:30 – 06:00L. 3.0 SCOPE & LOCATION OF WORKS
3.1 The required working locations will be as follows;
 Sunday 13th and Monday 14th January – Taxiway Juliet‐Echo.
 Tuesday 15th – Thursday 17th January – Taxiways Juliet (J3 and J4) and Taxiway Alpha (A1).
 Sunday 20th and Monday 21st January – Taxiway Juliet‐Foxtrot.
 Tuesday 22nd – Thursday 24th January – Taxiway Bravo (B5‐B6).
3.2 The scope of work will involve a variety of repair methods including;
 PQX pavement bay replacement.
 Maxicrete repairs.
 Fastpatch and sub‐surface grout injection
 Asphalt inlay repairs
 Sealing of pavement cracks.
4.0 OPERATIONAL IMPLICATIONS
4.1 Taxiway Closures
4.1.1 The following schedule of nightly (22:30‐06:00L) taxiway closures will be required to facilitate the work; Taxiway Juliet‐Echo Closed Sunday 13th & Monday 14th January Taxiway Juliet‐Foxtrot Closed Sunday 20th & Monday 21st January Taxiway Bravo (B5‐B6) Closed Tuesday 22nd – Thursday 24th January
4.1.2 The required pavement repair work on Taxiways Juliet (J3‐J4) and Alpha (A1) will be carried out concurrent with a scheduled night‐time maintenance closure of Runway 05L‐23R, therefore no operational implications are anticipated.
4.1.3 All the aforementioned taxiways will be fully operational outside of the nightly working times.
4.2 Stand Restrictions
4.2.1 Prior to works starting on Taxiway Juliet‐Echo, night‐stopping aircraft are to be parked on Stands 1, 5, 7, 9, 11, 15 and 16. 4.2.1.1 As part of the night‐time works on Taxiway Juliet‐Echo, the replacement of 1 x failed pavement bay at the rear of Stand 16 will be carried out. As such, Stand 16 will be closed overnight on either Sunday 13th or Monday 14th January.
4.2.2 Prior to works starting on Taxiway Juliet‐Foxtrot, night‐stopping aircraft are to be parked on Stands 42, 43 and 44.
4.2.3 The works on Taxiway Bravo (B5‐B6) will be managed such that aircraft access to either Taxiway Juliet‐ Echo or Juliet‐Foxtrot, and the stands served by those taxiways will be retained whilst work is in progress.
4.3 Aircraft Pushback Manoeuvres
4.3.1 Whilst night‐time work is in progress on Taxiway Juliet‐Echo, aircraft pushbacks from Stands 1, 5, 7, 9, 11, 15, 16, 17, 18 and 41 will not be possible.
4.3.2 Whilst night‐time work is in progress on Taxiway Juliet‐Foxtrot, aircraft pushbacks from Stands 17, 18, 41, 42, 43 and 44 will not be possible.
4.3.3 Whilst night‐time work is on progress on Taxiway Bravo (east of B6) aircraft pushbacks from Stand 44 will not be possible. Additionally, non‐standard aircraft pushbacks will be required for Stands 17, 18, 41, 42 and 43, with all aircraft being pushed back to face the terminal building, before taxiing out via Taxiway Juliet‐Echo.
4.3.4 Whilst night‐time work is in progress on Taxiway Bravo (west of B6) aircraft pushbacks will not be possible from Stands 11 and 15. Additionally, non‐standard aircraft pushbacks will be required for Stands 1,
 
My apologies for the late posting of this OAN

OAN 130-2018 – CHRISTMAS AND NEW YEAR RUNWAY OPERATING HOURS (WINTER 2018/19)
OAN REF:- 130/2018 DATE OF ISSUE:- 20/12/18 EFFECTIVE DATE:- 20/12/18 EXPIRY DATE:- 01/01/2019
1.0 SUMMARY
1.1 During the Christmas period, dual-runway operating hours will operate based on seasonal demand.
2.0 PROGRAMME
2.1 Standard dual-runway operating hours will be altered on Monday 24th December, Tuesday 25th December and Monday 31st December 2018 in line with demand for the Christmas and New Year season.
3.0 STANDARD RUNWAY OPERATING HOURS (Monday to Friday Inclusive)
3.1 Runway 05L/23R and 05R/23L will be in operation between 06:30hrs - 10:30hrs and 16:00hrs – 20:00hrs. Runway 05L/23R will be in operation as a single runway at all other times. All times quoted in this Operational Advice Notice are local.
3.2 Monday 24 th December 2018
3.2.1 Standard dual-runway operating hours will be in adhered to, but if demand levels reduce, runway 2 may be closed on the authority of the ATC Watch Manager and the Airfield Duty Manager, resulting in a single runway operation.
3.3 Tuesday 25th December 2018
3.3.1 Single runway operations will be in place on Christmas day due to the anticipated reduced demand levels.
3.4 Monday 31st December 2018
3.4.1 Standard dual-runway operating hours will be in adhered to, but if demand levels reduce, runway 2 may be closed on the authority of the ATC Watch Manager and the Airfield Duty Manager, resulting in a single runway operation.
4.0 FURTHER INFORMATION
4.1 For further information, please contact the Airfield Duty Manager on telephone number +44 (0)161 4xxx
 

Upload Media

Postimages.org logo
Postimages.org is an external site offering FREE image hosting and optional paid subscription hosting. The site provides ready‑to‑use coding you can paste directly into your forum posts. Recommended size: 1024 × 768. You can continue to use your Forums4Airports allowance as per your membership level. Attachments can be managed through your profile settings by clicking on your Avatar. Forums4Airports is not affiliated with postimages.org

Remove Advertisements

Subscribe to help support your favourite forum and in return we'll remove all our advertisements. Your contribution will help to pay for things like site maintenance, domain name renewals and annual server charges.



Forums4aiports
Subscribe

NEW - Profile Posts

I've added a link to Postimages.org as an alternative option for posting images here on Forums4airports. You can continue to post images with us but for prolific posters who love to share lots of images, this might be a better option for you.
All checked in for my flight to Sydney from Manchester via Heathrow. Been waiting for this trip for nearly a year and now tomorrow I'll finally head to Australia and New Zealand!
If anyone would like to share their local airport news right here in our news area let me know so I can give you the correct permissions to do so. It only takes a couple of minutes to upload a news story with an accompanying image. The news items can then be shared on the site homepage by you. #TakePart #Forums4airports Bring the news to one place!
survived a redundancy scenario where I work for the 3rd time. Now it looks likely I will get to cover work for 2 other teams.. Pretty please for a payrise? That would be a no and so stay on the min wage.
Live in Market Bosworth and take each day as it comes......
Well it looks like I'm off to Australia and New Zealand next year! Booked with BA from Manchester via Heathrow with a stop in Singapore and returning with Air New Zealand and BA via LAX to Heathrow. Will circumnavigate the globe and be my first trans-Pacific flight. First long haul flight with BA as well and of course Air NZ.

Trending Hashtags

Advertisement

Back
Top Bottom
  AdBlock Detected
Sure, ad-blocking software does a great job at blocking ads, but it also blocks some useful and important features of our website. For the best possible site experience please take a moment to disable your AdBlocker.