OAN 034/2022 – SCHEDULED RUNWAY 05L-23R NIGHT-TIME MAINTENANCE CLOSURES & NORTHSIDE TAXIWAY REPAIRS.
OAN REF:‐ 034/2022 DATE OF ISSUE:‐ 22/06/22 EFFECTIVE DATE:‐ 05/07/22 EXPIRY DATE:‐ 08/07/22
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
1.1 Runway 05L‐23R will be closed for three consecutive nights in early July to facilitate essential runway maintenance works within its strip and asphalt repairs on Taxiway Alpha. All flight operations will take place on Runway 05R‐23L whilst work is in progress.
2.0 PROGRAMME
2.1 Work will take place on the nights of Tuesday 5th to Thursday 7th July 2022, inclusive.
2.2 The planned nightly working hours will be 22:30 – 06:00L.
3.0 SCOPE & LOCATION OF WORKS
3.1 Overall, the scope and location of work will be:
 Asphalt repairs and overbanding on Runway 05L‐23R between Links Papa and Mike.
 Asphalt repairs on Taxiway Alpha at its junction with Taxiway Bravo.
 Overbanding on Taxiway Alpha from abeam Link Alpha‐Foxtrot to east of Intermediate Holding Point (IHP) A3.
 Routine runway maintenance tasks including AGL repairs and refreshment of painted ground markings.
4.0 OPERATIONAL IMPLICATIONS
4.1 Runway Operations
4.1.1 During the Runway 05L‐23R closure period (22:30‐06:00L) all flight operations will take place on Runway 05R‐23L.
4.2 Taxiway Restrictions
4.2.1 Taxiway Alpha will be closed on the night of Thursday 7th July (22:30 – 06:00L) between IHP A2 and its junction with Taxiway Bravo.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 In the event of forecast low visibility, the planned work will be cancelled and Runway 05L‐23R will remain open.
5.2 In the event of un‐forecast reduced visibility conditions (meeting the criteria for LVP Alert) during the Runway 05L‐23R closure period when work has begun on the runway paved surface, the aerodrome will close to flight operations whilst the runway is recovered. An ‘AD Closed’ NOTAM will be issued in such circumstances.
 
NOTAMS - 29th June -1st July as at 29th June 2022

EGCC (MANCHESTER)
Q)EGTT/QOBCE/IV/M/AE/000/005/5322N00216W001
B)2204110800 C)2207112359
E)LIT CRANE OPR 532159.79N 0021625.19W (1433M, 003 DEG MAG FM
MANCHESTER ARP) MAX HGT 415FT AMSL, 183FT AGL
A2798/22
Q)EGTT/QOBCE/IV/M/AE/000/005/5329N00217W001
B)2205020001 C)2207302359
E)CRANE. CONSTRUCTION SITE CRANE OPR AT PSN 532831N 0021706W
(SALFORD, GREATER MANCHESTER). UP TO 384FT AGL/484FT AMSL. FOR INFO
CONTACT 07854 888796. ON EXPIRY OF THIS NOTAM DETAILS WILL BE
INCLUDED IN THE UK AIP ENR 5.4 2022-05-0011/AS8
A1191/22
Q)EGTT/QOBCE/IV/M/AE/000/006/5328N00215W001
B)2206090001 C)2208092359
E)CRANE OPERATING AT PSN: 532816N 0021441W (MANCHESTER). UP TO
427FT AGL/535FT AMSL. FOR INFO CONTACT 07833 258238. ON EXPIRY OF
THIS NOTAM DETAILS WILL BE INCLUDED IN THE UK AIP ENR 5.4.
2022-06-0579/AS8.
A4294/22
Q)EGTT/QMRAH/IV/NBO/A/000/999/5321N00217W005
B)2206090501 C)2209071900
E)DAILY DUAL RWY OPR HR
MON-FRI 0515-1900
SAT 0515-1500
SUN 0515-0830 AND 1200-1900.
SINGLE RWY OPERATIONS RWY 05L/23R AT ALL OTHER TIMES.
A4346/22
Q)EGTT/QWULW/IV/BO/AW/000/006/5325N00236W002
B)2206100700 C)2207101700
D)0700-1700
E)UAS OPR WI 0.5NM RADIUS OF 532430N 0023540W (WARRINGTON,
CHESHIRE) MAX HGT 300FT AGL. FOR INFO 07946 345798.
2022-06-0630/AS2
F)SFC G)570FT AMSL
H3838/22
Q)EGTT/QOBCE/IV/M/AE/000/005/5328N00215W001
B)2206200001 C)2208192259
E)CRANES OPERATING AT PSN: 532816N 0021446W (MANCHESTER). UP TO
366FT AGL/476FT AMSL. FOR INFO CONTACT 07833 258238. ON EXPIRY OF
THIS NOTAM DETAILS WILL BE INCLUDED IN THE UK AIP ENR 5.4.
2022-06-0694/AS8.
A4416/22
Q)EGTT/QWELW/IV/BO/AW/000/999/5324N00217W002
B)2206271700 C)2207012200
D)27 1700-2200, JUN 28-JUL 01 1900-2200
E)SEARCHLIGHT DISPLAY WI 1NM RADIUS: 532412N 0021643W (WYTHENSHAWE
PARK, MANCHESTER, GREATER MANCHESTER). FOR INFO 07786 062451.
2022-06-0916/ AS2.
F)SFC G)UNL
H4275/22
Q)EGTT/QWELW/IV/BO/AW/000/999/5324N00217W002
B)2207010500 C)2207022300
D)01 0500-2300, 02 1800-2300
E)TERMINATED LASER DISPLAY WI 1NM RADIUS 532412N 0021643W
(WYTHENSHAWE PARK, MANCHESTER). FOR INFO 07837 582640.
2022-07-0205/AS2.
F)SFC G)UNL
H4532/22
Q)EGTT/QWALW/IV/M/AW/000/020/5324N00217W003
B)2207021300 C)2207031450
D)02 1300-1345, 03 1405-1450
E)FLYPAST WI 2NM RADIUS: 532415N 0021643W (WYTHENSHAW PARK,
GREATER MANCHESTER) 2022-07-0137/AS1.
F)SFC G)2000FT AMSL
H4388/22
Q)EGTT/QMRLC/IV/NBO/A/000/999/5321N00217W005
B)2207052130 C)2207080500
D)2130-0500
E)RWY 05L/23R CLSD DUE WIP, ALL FLIGHT OPERATIONS TO USE RWY
05R/23L.
THE WIP WILL BE CANCELLED IN THE EVENT OF FORECASTED LVP AND
RWY 05L/23R WILL REMAIN OPEN. FLIGHT CREWS SHOULD CONSIDER
ADDITIONAL FUEL UPLIFT AT ORIGIN DUE POTENTIAL FOR INCREASED AIR
HOLDING
A4901/22
Q)EGTT/QFULT/IV/NBO/A/000/999/5321N00217W005
B)2207112100 C)2207120230
E)ACFT FUEL HYDRANT SHUTDOWN FOR PLANNED MAINTENANCE. HYDRANT WILL
REMAIN OPERATIONAL FOR THE LAST SCHEDULED PLANE FUELLING EACH NIGHT.
ANY SCHEDULED FLIGHT WI PLANNED CLOSURE TIMES REQUIRING FUEL UPLIFT
SHOULD CONSIDER ADDITIONAL UPLIFT AT ORIGIN. HYDRANT WILL BE
OPERATIONAL PRIOR TO THE FIRST SCHEDULED DEPARTURE DAILY. TERMINAL
ONE AND TERMINAL THREE AFFECTED.
A4925/22
END.
 
But isn't the PIA / Jordan Aviation an established service with existing slots?
 
But isn't the PIA / Jordan Aviation an established service with existing slots?

Looking at the daily movements that @Scottie Dog provides, MAN has been handling over the 475 movements that they’re planning on capping movements at - it has been 500-550 depending on the day recently.

Can’t see how some existing flights won’t affected in that case?
 
Interesting that LGW's reduction from about 900 daily movements to 850 is an average of 5.6%.
Using the 550 figure for MAN (it's been higher on odd days), that would be a 14% reduction.
What happens after 8th July review is perhaps less clear.
 
Can I suggest that this discussion is more suitable to the Manchester Movements & Logs pages which can be found on the following link:


I'll post a brief resume of June movement numbers shortly.
 
OAN 038/2022 – SCHEDULED RUNWAY 05L-23R NIGHT-TIME MAINTENANCE CLOSURES & NORTHSIDE TAXIWAY REPAIRS.
OAN REF: 038/2022 DATE OF ISSUE: 19/07/22 EFFECTIVE DATE: 02/08/22 EXPIRY DATE: 05/08/22
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF 1.0
SUMMARY
1.1 Runway 05L‐23R will be closed for three consecutive nights in early August to facilitate essential runway maintenance works within its strip and asphalt repairs on Taxiway Alpha. All flight operations will take place on Runway 05R‐23L whilst work is in progress.
2.0 PROGRAMME
2.1 Work will take place on the nights of Tuesday 2nd to Thursday 4th August 2022, inclusive.
2.2 The planned nightly working hours will be 23:59 – 06:00L, with work concluding on the morning of Friday 5th August.
3.0 SCOPE & LOCATION OF WORKS
3.1 Overall, the scope and location of work will be:
 Asphalt repairs on Runway 05L‐23R, immediately east of Link Foxtrot.
 Asphalt repairs on Taxiway Alpha in the vicinity of Intermediate Holding Point (IHP) A3.
 Routine runway maintenance tasks including AGL repairs and refreshment of painted ground markings.
4.0 OPERATIONAL IMPLICATIONS
4.1 Runway Operations
4.1.1 During the Runway 05L‐23R closure period (23:59‐06:00L) all flight operations will take place on Runway 05R‐23L.
4.2 Taxiway Restrictions
4.2.1 Taxiway Alpha will be closed on the night of Thursday 4th August (23:59 – 06:00L) between IHP A2 and its junction with Taxiway Bravo.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 In the event of forecast low visibility, the planned work will be cancelled and Runway 05L‐23R will remain open.
5.2 In the event of un‐forecast reduced visibility conditions (meeting the criteria for LVP Alert) during the Runway 05L‐23R closure period when work has begun on the runway paved surface, the aerodrome will close to flight operations whilst the runway is recovered. An ‘AD Closed’ NOTAM will be issued in such circumstances.
 
OAN 039/2022 – X SUBSTATION EXTENSION
OAN REF:- 039/2022 DATE OF ISSUE:- 19/07/2022 EFFECTIVE DATE:- 08/08/2022 N/A EXPIRY DATE:- 25/01/2023
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
1.1 A six-months programme of work to extend the existing X Substation, located under the Pier C Satellite Lounge. During these works, access to the Potable Water Fill Point and the toilet facilities will be maintained.
2.0 PROGRAMME
2.1 The overall programme of work will commence on Monday 8th August 2022 and is scheduled to be completed by Sunday 25th January 2023.
2.2 Daily working hours will be 07:30 – 17:00 local, Working Monday to Friday.
3.0 SCOPE & LOCATION OF WORKS
3.1 Overall, the scope of work will involve the following tasks:
• Set up of the works compound.
• Building work to extend the substations footprint.
3.2 All work will take place under the Satellite Lounge, which is situated at the end of Pier C, at the head of Stands 31/32.
4.0 OPERATIONAL IMPLICATIONS
4.1 The Potable Water Supply has been relocated under the Satellite Lounge and will be available for use throughout the works.
4.2 Access to the EBT charging points and the airside toilet facilities in this area will be maintained.
4.3 The walking route to and from the EBT charging points and the toilets will be temporarily diverted around the outside of the building.
4.4 The work should not impact turnround activity on Stands 29, 31 or 32.
4.5 The changeover within the substation will take place circa December 2022. A separate OAN will be published closer to the time highlighting any operational implications.
5.0 CONTRACTOR, MANPOWER & EQUIPMENT
5.1 W H Good will be the contractor carrying out the works.
5.2 Manpower will be up to 4 operatives utilising 1x van.
6.0 LOW VISIBILITY PROCEDURES (LVP)
6.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility.
6.2 Work may continue during periods of low visibility at the discretion of the Airfield Duty Manager.
 
OAN 040/2022 – INSTALLATION OF MAN-TP SITE WELFARE CABIN DRAINAGE.
OAN REF:‐ 040/2022 DATE OF ISSUE:‐ 20/07/22 EFFECTIVE DATE:‐ 01/08/22 EXPIRY DATE:‐ 12/08/22
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
1.1 An overall programme of up to ten working days to connect the recently installed MAN‐TP site welfare cabins located adjacent to Stand 201 to the foul drainage system. To facilitate the work a temporary diversion of the section of apron road that links the Terminal 2 rear and head of stand roads will be required. Vehicular access to the nearby airside vehicle refuelling point will be retained at all times.
2.0 SCOPE AND LOCATION OF WORKS
2.1 The scope of work will be as follows:
 1 x excavation within the apron road system adjacent to Stand 201.
 Installation and connection of drainage pipework.
 Installation of new pit cover.
 Reinstatement of excavated pavement.
 Minor reconfiguration of apron road markings.
2.2 All work will take place within a temporarily closed section of the apron road system, namely, the link road between rear and of head stands, adjacent to Stand 201.
3.0 PROGRAMME
3.1 The programme of work will commence on Monday 1st and will be completed by Friday 12th August 2022.
3.2 All work will take place during daylight hours, Monday – Friday.
4.0 OPERATIONAL IMPLICATIONS
4.1 For the duration of the works programme, a demarked apron road diversion will be in place H24.
4.2 The pedestrian route leading from West Gate along the head of Stand 201 will remain available at all times. The interface between the diverted apron road system and pedestrian walkway will be clearly demarked, however pedestrians should remain vigilant whilst approaching and crossing the diverted portion of apron road.
4.3 A contractor banksman will be on site during daily working times to assist with the management of contractor traffic, pedestrians, and general apron road traffic.
4.4 Access to the airside vehicle refuelling point adjacent to Stand 201 will be retained at all times.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 The work will have no impact on the airport’s ability to operate during periods of low visibility.
 
OAN 039/2022 – X SUBSTATION EXTENSION
OAN REF:- 039/2022 DATE OF ISSUE:- 19/07/2022 EFFECTIVE DATE:- 08/08/2022 N/A EXPIRY DATE:- 25/01/2023
PLEASE ENSURE THIS INFORMATION IS PROMULGATED TO ALL STAFF
1.0 SUMMARY
1.1 A six-months programme of work to extend the existing X Substation, located under the Pier C Satellite Lounge. During these works, access to the Potable Water Fill Point and the toilet facilities will be maintained.
2.0 PROGRAMME
2.1 The overall programme of work will commence on Monday 8th August 2022 and is scheduled to be completed by Sunday 25th January 2023.
2.2 Daily working hours will be 07:30 – 17:00 local, Working Monday to Friday.
3.0 SCOPE & LOCATION OF WORKS
3.1 Overall, the scope of work will involve the following tasks:
• Set up of the works compound.
• Building work to extend the substations footprint.
3.2 All work will take place under the Satellite Lounge, which is situated at the end of Pier C, at the head of Stands 31/32.
4.0 OPERATIONAL IMPLICATIONS
4.1 The Potable Water Supply has been relocated under the Satellite Lounge and will be available for use throughout the works.
4.2 Access to the EBT charging points and the airside toilet facilities in this area will be maintained.
4.3 The walking route to and from the EBT charging points and the toilets will be temporarily diverted around the outside of the building.
4.4 The work should not impact turnround activity on Stands 29, 31 or 32.
4.5 The changeover within the substation will take place circa December 2022. A separate OAN will be published closer to the time highlighting any operational implications.
5.0 CONTRACTOR, MANPOWER & EQUIPMENT
5.1 W H Good will be the contractor carrying out the works.
5.2 Manpower will be up to 4 operatives utilising 1x van.
6.0 LOW VISIBILITY PROCEDURES (LVP)
6.1 Overall, the work has no impact on the airport’s ability to operate during periods of low visibility.
6.2 Work may continue during periods of low visibility at the discretion of the Airfield Duty Manager.

Out of interest…what is the Pier C satellite lounge?
I assume this means pier C is with us for the long term…
 
So if they are amending the infrastructure under the satellite does this mean the satellite is staying for a prolonged period? It was earmarked for demolition.
 
There was doubt about the actual pier being demolished, but the circular satellite was almost certainly going to be demolished.
I beg to differ. There was doubt if all the gates would remain in use in the satellite but by summer 2018 it was uncertain if the satellite would go.
 
All the renders I’ve seen, plus the general (internal) chatter had signified the end of the satellite. C-pier did appear to remain in some of the later renders, in some form, but as said, all the renders J saw had the actual satellite gone.
 
I may well be wrong but I seem to recall the plan at one stage included the provision of 2 new stands at the southern end of T2 as part of the TP, which would have meant at least part if not all Pier C going. At a different time, wasn't there plans in the TP for 4 piers on T2? I imagine a 4th pier could have impinged on T1 Pier C anyway but frankly I've lost track of all the changes and their sequence.
 

Upload Media

Remove Advertisements

Subscribe to help support your favourite forum and in return we'll remove all our advertisements. Your contribution will help to pay for things like site maintenance, domain name renewals and annual server charges.



Forums4aiports
Subscribe

NEW - Profile Posts

If anyone would like to share their local airport news right here in our news area let me know so I can give you the correct permissions to do so. It only takes a couple of minutes to upload a news story with an accompanying image. The news items can then be shared on the site homepage by you. #TakePart #Forums4airports Bring the news to one place!
survived a redundancy scenario where I work for the 3rd time. Now it looks likely I will get to cover work for 2 other teams.. Pretty please for a payrise? That would be a no and so stay on the min wage.
Live in Market Bosworth and take each day as it comes......
Well it looks like I'm off to Australia and New Zealand next year! Booked with BA from Manchester via Heathrow with a stop in Singapore and returning with Air New Zealand and BA via LAX to Heathrow. Will circumnavigate the globe and be my first trans-Pacific flight. First long haul flight with BA as well and of course Air NZ.
15 years at the same company was reached the weekend before last. Not sure how they will mark the occasion apart from the compulsory payirse to minimum wage (1st rise for 2 years; i was 15% above it back then!)
Ashley.S. wrote on Sotonsean's profile.
Welcome to the forum, I was born and bred in Southampton.

Trending Hashtags

Advertisement

Back
Top Bottom
  AdBlock Detected
Sure, ad-blocking software does a great job at blocking ads, but it also blocks some useful and important features of our website. For the best possible site experience please take a moment to disable your AdBlocker.