Aviador said:
Does that mean the airport no longer has to commit to starting the external works before the three years is up?
I don't think your pdf link is working because it is http(s) 's' for secure. If you download it you should be able to submit it to the forum as an attachment.
It wouldn't let me attach the file. I got the message
The extension pdf is not allowed.
But to answer the question, then no, the airport still have to comply with the 3 year time limit. But what the statement below shows, is that what they are proposing to the council is that "forecourt works" mark the start of the terminal develoment.
"Condition 1 - following discharge of pre-commencement conditions,
the forecourt works will begin, the first phase of the terminal works"
So, they are in the process of getting the pre-commencement conditions discharged - which in English is that the council will agree that all of things the airport need to do before any work can start, have been done and the airport are free to start work
The airport will then commence some "forecourt works" which they and the council will agree is the start of the of the development and therefore the condition that work must have started by December 2012 will have been met. As there is no limit (that I can see) on when the work has to be completed by, it will be up to the airport has to how quickly they wish to complete this.
When I spoke to the management in November, the intention was to build the external structure first and then the internal mods would follow. It now seems they will go the other way round and modify the existing first floor area first and then extend it out into the forecourt as a second phase at a later date - not withstanding that they obviously are planning to do something in the airport forecourt that is significant enough to satisfy the council that work has begun. There are rules that mean things like moving the drains or doing soil sampling cannot be counted as the start of the development. so it will be interesting to see what this is.
It seems obvious to me that with the economy still fragile and the comments Heather mentioned about the impact of high oil prices, that the management and the owners do not have enough confidence to commit to the full extension. They will have a much better idea than us about the plans airlines have for next summer and to what extent more capacity will be needed in the short term. Many I'm sure will say it is needed now ! That they are committing to something - up to £7m including VAT - is probably a good sign that, assuming no shocks and surprises, they believe a rise in passenger numbers next summer is likely.
Equally, I suspect they aren't expecting in excess of 4 million passengers within the next 18 months or so, so they have decided on approach which means they don't have to spend all of the money in one go, but also that they don't have to go back for planning permission