Leeds Bradford: Infrastructure & Construction Updates

  • Thread starter Thread starter Aviador
  • Start date Start date
  • Tagged users Tagged users None
Use this prefix for new threads for Leeds Bradford Airport
Thanks for sharing that.

How much further back have they pushed it, can you tell?
 
This has now closed so hopefully things will start moving soon.

6.8mppa and 55.9m spend

Leeds Bradford Airport is seeking to appoint a suitable Main Contractor to work on a design and build project to enhance the facilities and passenger experience through:
• Re-planning of the Passenger Search Area, and modelling to demonstrate capacity to manage 6.8 MPPA in line with the DfT 2024 compliance requirements.
• Arrivals Baggage offload / passenger routes resolved with utilisation of basement for arrivals baggage offload.
• Additional Reclaim carousels, and relocated immigration hall integrated into the Layouts
• New Retail layouts provided in outline
• PRM routes to enable enjoyment of the whole of the LBA passenger experience.
• Improved vertical circulation cores and routes.

Further details are provided in the RIBA Stage 2 report issued as part of the PQQ process. It is currently intended that works will be delivered over two phases:
1. Phase 1 - New Build Arrivals Terminal Building (approximately £28.5m budget cost)
2. Phase 2 - Remodelling to the existing Terminal (approximately £27.4m budget cost)


In addition to this there is circa £3.3m of ancillary works to support the phases above that will from part of the overall project. Client fitout works of circa £8m in value will need to be considered in the coordination of the design

Additional information:
Documents can be accessed at https://in-tendhost.co.uk/intendsharedservices/


#LBATerminalTransformation
 
This has now closed so hopefully things will start moving soon.

6.8mppa and 55.9m spend

Leeds Bradford Airport is seeking to appoint a suitable Main Contractor to work on a design and build project to enhance the facilities and passenger experience through:
• Re-planning of the Passenger Search Area, and modelling to demonstrate capacity to manage 6.8 MPPA in line with the DfT 2024 compliance requirements.
• Arrivals Baggage offload / passenger routes resolved with utilisation of basement for arrivals baggage offload.
• Additional Reclaim carousels, and relocated immigration hall integrated into the Layouts
• New Retail layouts provided in outline
• PRM routes to enable enjoyment of the whole of the LBA passenger experience.
• Improved vertical circulation cores and routes.

Further details are provided in the RIBA Stage 2 report issued as part of the PQQ process. It is currently intended that works will be delivered over two phases:
1. Phase 1 - New Build Arrivals Terminal Building (approximately £28.5m budget cost)
2. Phase 2 - Remodelling to the existing Terminal (approximately £27.4m budget cost)


In addition to this there is circa £3.3m of ancillary works to support the phases above that will from part of the overall project. Client fitout works of circa £8m in value will need to be considered in the coordination of the design

Additional information:
Documents can be accessed at https://in-tendhost.co.uk/intendsharedservices/


So it begins......£67.2m in total.
 
Last edited:
I assumed the plans had already been drawn up and it was just a main contractor for building to those plans.
 
I assumed the plans had already been drawn up and it was just a main contractor for building to those plans.
The exterior plans are drawn up and they will have to comply with what was given planning consent. Internally, the airport will have ideas but the contractor is responsible for designing them and ensure they work. Hence it's a 'Design and Build' scheme with the contractor responsible. It usually saves time that way.
 
Well £67.2m is better than doing nothing, but half off it is been spent on remodeling the existing terminal in phase 2.

Don't get me wrong it good to see that things finally seem to be moving along. But I won't be happy until we see a main contractor on site and steel work going up.

That's the builder in me, kinda thing!
 
Well £67.2m is better than doing nothing, but half off it is been spent on remodeling the existing terminal in phase 2.

Don't get me wrong it good to see that things finally seem to be moving along. But I won't be happy until we see a main contractor on site and steel work going up.

That's the builder in me, kinda thing!
Re-modelling is more complex and therefore more expensive than building from scratch, so they will see less for their money in phase 2 than phase 1, but at least they are throwing some significant cash into it,.and not just going through the motions. They will get quite a lot done for that money..
 
I wonder how long they have pencilled in for the tender process. It will be a lot of work.
 
However long this all takes there have been suggestions it will be 2024 when new airlines should hopefully come to LBA, so some improvements needed by then. However when this is all complete things will be a massive upgrade on what we currently have, and whilst not the shiny new terminal we all ideally wanted, this should be welcomed with open arms
 
However long this all takes there have been suggestions it will be 2024 when new airlines should hopefully come to LBA, so some improvements needed by then. However when this is all complete things will be a massive upgrade on what we currently have, and whilst not the shiny new terminal we all ideally wanted, this should be welcomed with open arms
2024 seems optimistic to me .
 
Agreed, so question is will this deter new airlines until fully complete? But I suppose, if like Wizz, they can operate at quieter Terminal times then there could be some increase for 2024. Will certainly be disappointed if nothing happening by 2025. Another way to look at this upgrade is that if LBA had never even suggested a brand new terminal then I suspect we would all be jumping through hoops at this
 
I note the contract start date is stated as 1 July 2023.
Which seems about right as it allow from now until then for contractors to visit site, undertake surveys, consider how they intend to carry out the work, assess the materials needed, price them up, work out costs, submit a tender, await the outcome, probably attend an interview (usually 3 contractors), and eventually, someone will be awarded the contract. For a project on this scale, 6 months seems about right from advertising to contract start up. Figuring out how to transform the existing terminal whilst keeping it operational will, in itself, be the subject of much consideration and discussion..
 

Remove Advertisements

Subscribe to help support your favourite forum and in return we'll remove all our advertisements. Your contribution will help to pay for things like site maintenance, domain name renewals and annual server charges.



Forums4aiports
Subscribe

Heads Up!

For some weird reason, my days off work tend to involve being out of my flat by 5am and not getting back until 10pm. Back to work and the regular "fix" of 7.40am to 7.15pm hours
Heatwave Mk2 next week?
Some explosive weather build-ups currently in the North of England. What is it like where you are?
LBA: B737-300 G-GDFK empty down to Paris at 16:15 to operate the return LS268 back to Leeds 20:00 ETA where it will then operate the delayed LS265 to Malaga 20:40ETD
LBA: Albastar B737-800 EC-MUB positioning in tommorow afternoon from Gatwick 15:45 to operate a charter to Lourdes/Tarbes on Friday afternoon 14:00 AP7721 STC
I don't believe I am quite covering enough roles at work. Its now 4 on a bad day, 5 on a good day and there is scope for a 6th and 7th role. Still on minimum pay but had the biggest payrise in the company,